App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?

ARs. 400

BRs. 500

CRs. 600

DRs. 200

Answer:

B. Rs. 500

Read Explanation:

Total work = LCM of 10, 15 = 30 Efficiency of A = Total work / Time taken = 30 / 10 = 3 Efficiency of B = Total work / Time taken = 30 / 15 = 2 The efficiency of both = Efficiency of A + Efficiency of B = 3 + 2 = 5 Amount per day = Total amount / Efficiency of both = 1250 / 5 = Rs. 250 The amount B get = Amount per day x Efficiency of B = 250 x 2 = Rs. 500


Related Questions:

A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.
Anil can do a piece of work in 4 hours. Ashok can do it in 8 hours. With the assistance of Robin, they completed the work in 2 hours. In how many hours can Robin alone do it?
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?
If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?
15 ജോലിക്കാർ 4 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്തു തീർക്കുന്നു. അതേ ജോലി ചെയ്യാൻ 5 പേരുണ്ടെങ്കിൽ എത്ര ദിവസം വേണം ?