App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can complete a work in 10 days and 15 days, respectively. They got a total of Rs. 1,250 for that work. What will be B’s share?

ARs. 400

BRs. 500

CRs. 600

DRs. 200

Answer:

B. Rs. 500

Read Explanation:

Total work = LCM of 10, 15 = 30 Efficiency of A = Total work / Time taken = 30 / 10 = 3 Efficiency of B = Total work / Time taken = 30 / 15 = 2 The efficiency of both = Efficiency of A + Efficiency of B = 3 + 2 = 5 Amount per day = Total amount / Efficiency of both = 1250 / 5 = Rs. 250 The amount B get = Amount per day x Efficiency of B = 250 x 2 = Rs. 500


Related Questions:

A, B, C can together complete the work in 12 days. If A is thrice faster than B, and B is twice faster than C, B alone can do the work in:
If 36 men can do some work in 25 days, then in how many days will 15 men do it?
Had been one man less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?
A ക്കും B ക്കും നാലുദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും A മാത്രം 12 ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കും B മാത്രം എത്ര ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കാൻ സാധിക്കും
A ഒരു ജോലി 20 ദിവസം എടുത്തു പൂർത്തിയാക്കുന്നു A യും B യും കൂടി ഒരുമിച്ച് ജോലി പൂർത്തീകരിക്കാൻ 12 ദിവസം എടുക്കും എന്നാൽ B മാത്രമായി പ്രസ്തുത ജോലി പൂർത്തീകരിക്കാൻ എത്ര ദിവസം എടുക്കും ?