Let total work = 1 unit.
A’s 1-day work = ( \frac{1}{25} )
B’s 1-day work = ( \frac{1}{30} )
Work done by A + B in 6 days:
(251+301)×6
=(1506+5)×6
=15011×6
=15066
=2511
Remaining work:
1−2511=2514
Now, A + P complete this in 8 days:
(A + P one day work)=2514÷8=20014=1007
So,
251+P1=1007
P1=1007−251
=1007−1004
=1003
P=3100=3331 days
P alone will take(3331) days