A, B, and C can complete a certain task in 20, 30, and 60 days, respectively. How many days will it take for A to finish the work if he receives help from B and C every third day?

A15 days

B12 days

C10 days

D9 days

Answer:

A. 15 days

Read Explanation:

A can complete the work in 20 days.

So, A's 1-day work:

120\frac{1}{20}

B's 1-day work:

130\frac{1}{30}

C's 1-day work:

160\frac{1}{60}

On every third day, A gets help from B and C:

120+130+160\frac{1}{20}+\frac{1}{30}+\frac{1}{60}
=3+2+160=\frac{3+2+1}{60}
=110=\frac{1}{10}

Work done in 3 days

  • Day 1: A = (120)(\frac{1}{20})

  • Day 2: A =(120) (\frac{1}{20})

  • Day 3: A+B+C =(110) (\frac{1}{10})

120+120+110\frac{1}{20}+\frac{1}{20}+\frac{1}{10}
=15=\frac{1}{5}

So, in 3 days, they complete (15)(\frac15) of the work.

In 15 days:

5×15=15\times\frac15=1

Answer: 15 days


Related Questions:

7 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കാൻ 6 ദിവസം വേണം. അതേ ജോലി ഒരു ദിവസം കൊണ്ട്പൂർത്തിയാക്കാൻ എത്ര ആൾക്കാർ വേണം?
മനുവിന് ഒരു ജോലി ചെയ്യാൻ 10 ദിവസം വേണം അനുവിന് അത് ചെയ്ത് തീർക്കാൻ 15 ദിവസം വേണം. എങ്കിൽ രണ്ടു പേരും ചേർന്ന് ഈ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
Pravin can do a piece of work in 6 hours. Rishi can do it in 28 hours. With the assistance of Shan, they completed the work in 4 hours. In how many hours can Shan alone do it?
10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?