App Logo

No.1 PSC Learning App

1M+ Downloads
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

A$$7\frac{1}{2}$ days$

B8 days

C10 days

D7 days

Answer:

$$7\frac{1}{2}$ days$

Read Explanation:

Solution:

Given:

A can do a certain job in 12 days.

B is 60% more efficient than A.

Formula used:

work = efficiency × days

Calculation:

Let efficiency of A be 100.

The efficiency of B will be 160.

Ratio of efficiency A and B = 100 : 160 = 5 : 8

Total work = efficiency ratio of A × total days taken by A to finish work

⇒ 5 × 12 = 60 unit

Time taken by B to finish work = total work/efficiency ratio of B

608=712days\frac{60}{8}=7\frac{1}{2}days

B will finish the job in 712days7\frac{1}{2}days


Related Questions:

A and B together can do a piece of work in 12 days and A alone can complete the work in 18 days how long will B alone take to complete the job ?
After 63 litres of petrol was poured into an empty storage tank, it was still 10% empty. How much petrol (in litres)must be poured into the storage tank in order to fill it?
നാല് പേർ ചേർന്ന് ഒമ്പത് ദിവസം കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി ആറ് ദിവസം കൊണ്ട്തീർക്കണമെങ്കിൽ എത്ര ജോലിക്കാരെ കൂടി കൂടുതലായി വേണ്ടിവരും ?
Two pipes A and B can fill a tank in 6 hours and 8 hours respectivley. If both the pipes are opened together, then after how many hours should B be closed so that the tank is full in 4 hours ?
If 25 persons can complete a work in 140 days, then how many persons will be required to complete the same work in 70 days?