Challenger App

No.1 PSC Learning App

1M+ Downloads
A can do a certain job in 12 days. B is 60% more efficient than A. To do the same job B alone would take?

A$$7\frac{1}{2}$ days$

B8 days

C10 days

D7 days

Answer:

$$7\frac{1}{2}$ days$

Read Explanation:

Solution:

Given:

A can do a certain job in 12 days.

B is 60% more efficient than A.

Formula used:

work = efficiency × days

Calculation:

Let efficiency of A be 100.

The efficiency of B will be 160.

Ratio of efficiency A and B = 100 : 160 = 5 : 8

Total work = efficiency ratio of A × total days taken by A to finish work

⇒ 5 × 12 = 60 unit

Time taken by B to finish work = total work/efficiency ratio of B

608=712days\frac{60}{8}=7\frac{1}{2}days

B will finish the job in 712days7\frac{1}{2}days


Related Questions:

Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?
ഒരു ടാങ്കിൻറ നിർഗമന കുഴൽ തുറന്നാൽ 2 മണിക്കൂർ കൊണ്ട് നിറയും. ബഹിർഗമന കുഴൽ തുറന്നാൽ 3 മണിക്കൂർ കൊണ്ട് ടാങ്ക് കാലിയാവും. രണ്ട് കുഴലുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?
A pipe can fill a tank in 6 hours. Another pipe can empty the filled tank in 30 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days A finished the remaining work. In how many days A alone can finish the job?
16 ആളുകൾ 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. ഈ ജോലി 8 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ എത്ര ആളുകൾ കൂടുതലായി വേണം ?