A can do a certain work in 18 days. B is 25% less efficient than A. A alone worked for a few days and then, B joined him. Both worked together till the completion of the work. The entire work got completed in 12 days. For how many days did A and B work together?

A6

B4

C9

D8

Answer:

D. 8

Read Explanation:

Let A's efficiency be 100 units/day B's efficiency = (100 × 75/100) = 75 units/day Total work = (100 × 18) = 1800 units work alone by A be x days A and B work together = (12 – x) days (100 × x) + (100 + 75) × (12 – x) = 1800 100x + 1200 – 100x + 900 – 75x = 1800 2100 – 75x = 1800 75x = (2100 – 1800) 75x = 300 x = 4 days Time taken by A and B together to complete the work = (12 – x) = (12 – 4) days = 8 days


Related Questions:

X and Y can complete a piece of work in 8 days and 12 days, repectively. If they work on alternate days, with X working on the first day , how long will it take the duo to complete the same work?
6 ആളുകൾ ഒരു ജോലി 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു . എന്നാൽ ഒരാൾ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
Rishi can do a piece of work in 8 hours. Shan can do it in 12 hours. With the assistance of Veer, they completed the work in 3 hours. In how many hours can Veer alone do it?
Thers is an order of 19000 quantity of a particular product from a customer. The firm produces 1000 quantity of that product per day out of which 5% are unfit for sale. In how many days will the order be completed ?
A, B and C can do a work in 20, 30 and 60 days respectively. If total Rs, 3000 is given to them, then find their individual share.