A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?

A6 days

B12 days

C4days

D8 days

Answer:

A. 6 days

Read Explanation:

work done by A for 3 days = 3/12=1/4 Remaining work = 1 - 1/4 = 3/4 work done by (A+B) for 1 day=(3/4)*(1/3)=1/4 work done by B for 1 day=(1/4)-(1/12)=2/12=1/6. B alone will complete the work in 6 days


Related Questions:

Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
Pipes A and B can fill a tank in 16 hours and 24 hours, respectively, whereas pipe C can empty the full tank in 40 hours. All three pipes are opened together, but pipe A is closed after 10 hours. After how many hours will the remaining part of the tank be filled?

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in:

6 men can complete a work in 10 days. They start the work and after 2 days 2 men leave. In how many days will the work be completed by the remaining men?
A and B can complete a task together in 35 days. If A works alone and completes 5/7 of the task and then leaves the rest for B to complete by herself, it will take a total of 90 days to complete the task. How many days would it take A, the more efficient among the duo, to complete the entire work by herself?