A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?

A6 days

B12 days

C4days

D8 days

Answer:

A. 6 days

Read Explanation:

work done by A for 3 days = 3/12=1/4 Remaining work = 1 - 1/4 = 3/4 work done by (A+B) for 1 day=(3/4)*(1/3)=1/4 work done by B for 1 day=(1/4)-(1/12)=2/12=1/6. B alone will complete the work in 6 days


Related Questions:

A and B can together complete a task in 18 hours. After 6 hours A leaves. B takes 36 hours to finish rest of the task. How many hours would A have taken to do the task, if he worked alone?
A 6 ദിവസത്തിൽ ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയുകയും B 9 ദിവസங்களில் സ്ഥിരം ജോലി പൂർത്തിയാക്കാൻ കഴിയുകയും ചെയ്യുന്നു. ഇരുവരും ചേർന്ന് ഈ ജോലിയെ പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
A fort is provisioned for 32 days for some soldiers. After 4 days, a reinforcement of 150 soldiers arrived and the food will now last for 21 days only. How many soldiers were there in the fort in the beginning?
30 men working 5 hours a day can do a task in 16 days. In how many days will 40 men working 6 hours a day do the same task?