A job is completed by 10 men in 20 days and by 20 women in 15 days. How many days will it take for 5 men and 10 women to finish that work ?

A17 1/2

B17 1/7

C17

D17 1/120

Answer:

B. 17 1/7

Read Explanation:

10 men can complete the work in 20 days = 5 men can complete the work in 40 days 20 women can complete the work in 15 days = 10 women can complete the work in 30 days. 5 men and 10 women can complete the work in 40 x 30/40+30 days = 1200/70 = 120/70 = 17 1/7 days


Related Questions:

A and B undertake to do a piece of work for Rs. 330. A can do it in 11 days and B can do it in 22 days. With the help of C, they finish it in 6 days. How much should C be paid for his work?
Two pipes P and Q, together can fill a cistern in 20 minutes and P alone can in 30 miutes. Then Q alone can fill the cistern in?
ഒരു പരീക്ഷ തുടങ്ങാനായി ഒരു ബെല്ലടിക്കുകയും തുടർന്ന് ഓരോ അരമണിക്കൂർ കഴിയുമ്പോഴും ഓരോ ബെല്ലടിക്കുകയും ചെയ്യുന്നു. ആകെ 6 ബെല്ലടിച്ചുവെങ്കിൽ പരീക്ഷ സമയം എത്ര ?

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in:

A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. എന്നിരുന്നാലും, ജോലി പൂർത്തിയാകുന്നതിന് കുറച്ച് ദിവസങ്ങൾക്ക് മുമ്പ് A യ്ക്ക് പോകേണ്ടിവന്നു, അതിനാൽ ജോലി പൂർത്തിയാക്കാൻ ആകെ 16 ദിവസമെടുത്തു. A ക്ക് ഒറ്റയ്ക്ക് 21 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ, ആ ജോലി തീരുന്നതിന് എത്ര ദിവസം മുമ്പാണ് A വിട്ടുപോയത്?