Challenger App

No.1 PSC Learning App

1M+ Downloads
A job is completed by 10 men in 20 days and by 20 women in 15 days. How many days will it take for 5 men and 10 women to finish that work ?

A17 1/2

B17 1/7

C17

D17 1/120

Answer:

B. 17 1/7

Read Explanation:

10 men can complete the work in 20 days = 5 men can complete the work in 40 days 20 women can complete the work in 15 days = 10 women can complete the work in 30 days. 5 men and 10 women can complete the work in 40 x 30/40+30 days = 1200/70 = 120/70 = 17 1/7 days


Related Questions:

A ക്ക് ഒരു ജോലി 6 ദിവസം കൊണ്ടും B ക്ക് 4 ദിവസം കൊണ്ടും ചെയ്യാൻ കഴിയും. രണ്ടുപേരും ഒരുമിച്ച് പ്രവർത്തിച്ചാൽ എത്ര സമയമെടുക്കും?
A pipe can fill a tank in 9 hours. Another pipe can empty the filled tank in 36 hours. If both the pipes are opened simultaneously, then the time (in hours) in which the tank will be two-third filled, is
A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
ഒരു ടാങ്കിൽ വെള്ളം വരുന്ന രണ്ട് പൈപ്പുകൾ ഉണ്ട്. അവയിൽ ഒരു പൈപ്പ് തുറന്നാൽ 5 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും. മറ്റേതു തുറന്നാൽ 3 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും. രണ്ടു പൈപ്പുകളും ഒരുമിച്ച് തുറന്നിട്ടാൽ എത്ര മണിക്കൂർകൊണ്ട് ടാങ്ക് നിറയും ?
Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?