An airline has determined that 10 spare brake cylinders will give them stock out risk of 30%, whereas 14 will reduce the risk to 15% and 16 to 10%. It takes 3 months to receive items from supplier and the airline has an average of 4 cylinders per month. At what stock level should they reorder assuming that they wish to maintain 85% service level?

A12 items

B14 items

C26 items

D30 items

Answer:

C. 26 items

Read Explanation:

Lead time demand = 3 x 4 = 12 items, Safety Stock level should they reorder assuming that they wish to maintain 85% service level = 15% disservice it means 15% stock is out of risk, It is given that, 14 items will reduce the risk to 15%. Therefore, Reorder level = 12 + 14 = 26 items.


Related Questions:

Micro motion study is called
Which of the following is an example of flow production?
Which is the last stage of the product planning and development process?
What is the full form of MPS in manufacturing?
The layout of the aircraft manufacturing factory should be