Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.

    Aii only

    BNone of these

    Cii, iii

    DAll of these

    Answer:

    D. All of these