Challenger App

No.1 PSC Learning App

1M+ Downloads
Forms of freshly laid rcc work should not be struck for a period called .............................. until the concrete has reached a strength at least twice the stress to which the concrete may be subjected to at the time of removal of form work.

ABleeding time

BStripping time

CSetting time

DNone of the above

Answer:

B. Stripping time


Related Questions:

For concreting aggregate should be
The workability of concrete can be increased by which of the following?
The designation of standard recommended scales of 1:10 and 1: 20 is
Placing of concrete should be done at a temperature
Termites found in coastal regions of South India are called :