Forms of freshly laid rcc work should not be struck for a period called .............................. until the concrete has reached a strength at least twice the stress to which the concrete may be subjected to at the time of removal of form work.

ABleeding time

BStripping time

CSetting time

DNone of the above

Answer:

B. Stripping time