Challenger App

No.1 PSC Learning App

1M+ Downloads
If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

A38 days

B32 days

C40 days

D35 days

Answer:

C. 40 days

Read Explanation:

Solution:

Given:

12 men (M) can do the work in 54 days

20 women (W) can do the same work in 54 days

Concept used:

If n person can do the work in x days then 1 person can do the same work in nx days

If a person completes work in m days then the person will complete 1/m work in one day. 

Calculation:

12 men can do the work in 54 days 

⇒ 1 man can do the work in 12 × 54 = 648 days

⇒ 9 men can do the work in 648/9 = 72 days

⇒ 9 men can do 1/72 of work in 1 day

20 women can do the work in 54 days

⇒ 1 woman can do the work in 54 × 20 = 1080 days

⇒ 12 women can do the work in 1080/12 = 90 days

⇒ 12 women can do 1/90 of work in 1 day

⇒ 9 men and 12 women can do 1/72 + 1/90 work in a day

⇒ 9 men and 12 women can do (5 + 4)/90 work in a day

⇒ 9 men and 12 women can do 1/40 of work in 1 day

⇒ 9 men and 12 women can do 1 work in 1 × 40 days

∴ 9 men and 12 women can do 1 work in 40 days.

Alternate:

12 men can do the work in 54 days 

⇒ 1 man can do the work in 12 × 54 = 648 days

⇒ 9 men can do the work in 648/9 = 72 days

20 women can do the work in 54 days

⇒ 1 woman can do the work in 54 × 20 = 1080 days

⇒ 12 women can do the work in 1080/12 = 90 days


image.png

⇒ 9 men and 12 women can do work in 360/(5+4)

⇒ 9 men and 12 women can do work in 360/9

∴ 9 men and 12 women can do work in 40 days.


Short Cut:

Formula used:

M1 × T1 = M2 × T2

Where M is men and T is time

Calculation:

12M × 54 = 20W × 54

⇒ M/W = 5/3 or M = 5 and W = 3

Total work = No of Women × Efficiency ×  Days

20 × 3 × 54 = 3240

9M + 12W = 9 × 5 + 12 × 3 = 81

Time = 3240/81 = 40 days

∴ 9 men and 12 women can do work in 40 days.


Related Questions:

Pipes A, B and C can fill a tank in 10, 15 and 18 hours, respectively. A and C are opened for 5 hours, then only pipe A is closed and B is opened at the same time (with C). The total time taken to fill the tank completely is:
A ഒരു ജോലി 25 ദിവസംകൊണ്ടും B അതേ ജോലി 30 ദിവസംകൊണ്ടും പൂർത്തിയാക്കും. അവർ ഒരുമിച്ച് 5 ദിവസം ജോലി ചെയ്തതിന് ശേഷം A വിട്ടുപോയി. ബാക്കി ജോലി Bക്ക് പൂർത്തിയാക്കാൻ എത്ര ദിവസം വേണം?
If C alone can complete two-third part of a work in 12 days, then in how many days C can complete the whole work?
A ഒരു ജോലി 10 ദിവസം കൊണ്ട് പൂർത്തിയാക്കും. B അതേ ജോലി 15 ദിവസം കൊണ്ട് പൂർത്തിയാക്കും. B ആ ജോലി ആരംഭിച്ച് 5 ദിവസം ജോലി ചെയ്യും, അതിനുശേഷം A ആ ജോലി പൂർത്തിയാക്കും. A എത്ര ദിവസം ജോലി ചെയ്തു?
A ഒരു നിശ്ചിത ജോലി 4 മണിക്കൂർ കൊണ്ട് ചെയ്യാൻ കഴിയും. A യും B യും ചേർന്ന് ഒരേ ജോലി 2 മണിക്കൂർ കൊണ്ട് ചെയ്യുന്നു. B യും C യും ചേർന്ന് 3 മണിക്കൂറിനുള്ളിൽ ഇത് ചെയ്യുന്നു. C മാത്രം ജോലി ചെയ്യാൻ എത്ര സമയമെടുക്കും?