If 30 workers can do a work in 40 days. In how many days will 40 workers do the same work?

A30 days

B25 days

C35 days

D20 days

Answer:

A. 30 days

Read Explanation:

time taken by 40 workers = (30x40)/ 40 = 30 days


Related Questions:

A man, a woman and a boy can complete a work in 20 days, 30 days and 60 days respectively. How many boys must assist 2 men and 8 women so as to complete the work in 2 days?
24 people can finish a job by 10 days. How many days will be required to finish the same job by 8 people?
8 men or 10 women can finish a work in 50 days. How many days will 28 men and 15 women take to finish the job ?
Alice can do a piece of work in 10 days Anu can do the same work in 12 days and Meera do the work in 15 days. If they work together low long will they take to complete the work?

A can do 331333\frac{1}{3}% of a work in 10 days and B can do 662366\frac{2}{3}% of the same work in 8 days. Both together worked for 8 days then C alone completes the remaining work in 3 days. A and C together will complete 56\frac{5}{6} part of the original work in: