If 30 workers can do a work in 40 days. In how many days will 40 workers do the same work?A30 daysB25 daysC35 daysD20 daysAnswer: A. 30 days Read Explanation: time taken by 40 workers = (30x40)/ 40 = 30 daysRead more in App