If 30 workers can do a work in 40 days. In how many days will 40 workers do the same work?

A30 days

B25 days

C35 days

D20 days

Answer:

A. 30 days

Read Explanation:

time taken by 40 workers = (30x40)/ 40 = 30 days


Related Questions:

16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building?
A and B can do a work in 12 days, B and C in 15 days and C and A in 20 days. If A, B and C work together, they will complete the work in :
There are 3 taps, A, B and C, in a tank. These can fill the tank in 10 h, 20 h and 25 h, respectively. At first, all three taps are opened simultaneously. After 2 h, tap C is closed and tap A and B keep running. After 4 h, tap B is also closed. The remaining tank is filled by tap A alone. Find the percentage of work done by tap A itself.
A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. എന്നിരുന്നാലും, ജോലി പൂർത്തിയാകുന്നതിന് കുറച്ച് ദിവസങ്ങൾക്ക് മുമ്പ് A യ്ക്ക് പോകേണ്ടിവന്നു, അതിനാൽ ജോലി പൂർത്തിയാക്കാൻ ആകെ 16 ദിവസമെടുത്തു. A ക്ക് ഒറ്റയ്ക്ക് 21 ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ, ആ ജോലി തീരുന്നതിന് എത്ര ദിവസം മുമ്പാണ് A വിട്ടുപോയത്?
ഒരു ടാങ്കിന്റെ നിർഗമനകുഴൽ തുറന്നാൽ 9 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും.ബഹിർഗമന ടാപ്പ് തുറന്നാൽ 12 മണിക്കൂർ കൊണ്ട് ടാങ്ക് കാലിയാവുന്നു.രണ്ടു കുഴലുകളും ഒരുമിച്ചു തുറന്നാൽ എത്ര സമയം കൊണ്ട് ടാങ്ക് നിറയും?