App Logo

No.1 PSC Learning App

1M+ Downloads
If 36 men can do some work in 25 days, then in how many days will 15 men do it?

A50 days

B54 days

C56 days

D60 days

Answer:

D. 60 days

Read Explanation:

As we know,

⇒ M1 ×\times D1 = M2 ×\times D2

⇒ 36 ×\times 25 = 15 ×\times D2

⇒ D2 = (36×25)15\frac{(36\times{25})}{15}

⇒ D2 = 60 days


Related Questions:

A and B together complete a work in 8 days. If B is 25% more efficient than A, then in how many days will A alone complete the same work?
40 mechanics can repair a bike in 56 days. In how many days 32 mechanics will do the same work?
Harry and Larry can together plough the field in 5 days. Harry alone takes 8 days to plough the same field. In how many days can Larry alone plough the field?
A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in:
A bicycle is sold at a profit of 10%. Had it been sold for 900 less, there would have been a loss of 10%. The cost price of the bicycle is: