If 5 workers working 7 hours a day can finish the work in 4 days, then one worker working 10 hours a day can finish the same work in:

A8 days

B10 days

C20 days

D14 days

Answer:

D. 14 days

Read Explanation:

M1 D1 H1 = M2 D2 H2 D2 = (M1 D1 H1) / (M2 H2) = (5 x 7 x 4) / (1 x 10) = 14days


Related Questions:

Two pipes A and B can fill a cistern in 36 minutes and 48 minutes, respectively. Both the pipes are opened at the same time and pipe B is closed after some time. If the cistern gets filled in half an hour, then after how many minutes was pipe B closed?
Jitesh and Kamal can complete a certain piece of work in 18 and 17 days, respectively, They started to work together, and after 5 days, Kamal left. In how many days will Jitesh complete the remaining work?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
A, B എന്നിവർക്ക് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, A യ്ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് അതേ ജോലി ചെയ്യാൻ കഴിയും. B-ക്ക് മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ ഒരേ ജോലി ചെയ്യാൻ കഴിയും?
A , B എന്നിവർക്ക് യഥാക്രമം 15 ദിവസവും 10 ദിവസവും ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, പക്ഷേ 2 ദിവസത്തിന് ശേഷം Bക്ക് പോകേണ്ടി വന്നു, A മാത്രം ബാക്കിയുള്ള ജോലി പൂർത്തിയാക്കി. A പണി പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?