If 5 workers working 7 hours a day can finish the work in 4 days, then one worker working 10 hours a day can finish the same work in:

A8 days

B10 days

C20 days

D14 days

Answer:

D. 14 days

Read Explanation:

M1 D1 H1 = M2 D2 H2 D2 = (M1 D1 H1) / (M2 H2) = (5 x 7 x 4) / (1 x 10) = 14days


Related Questions:

Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?
A ഒരു ജോലി 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. അതേ ജോലി B, 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. എന്നാൽ A യും B യും ചേർന്ന് ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാം?
Abhay and Bharat can complete a certain piece of work in 17 and 10 days, respectively, They started to work together, and after 3 days, Bharat left. In how many days will Abhay complete the remaining work?
Two pipes A and B can fill a cistern in 3 hours and 5 hours respectively. Pipe C can empty in 2 hours. If all the three pipes are open, in how many hours the cistern will be full?
Anil can do a piece of work in 4 hours. Ashok can do it in 8 hours. With the assistance of Robin, they completed the work in 2 hours. In how many hours can Robin alone do it?