If 5 workers working 7 hours a day can finish the work in 4 days, then one worker working 10 hours a day can finish the same work in:

A8 days

B10 days

C20 days

D14 days

Answer:

D. 14 days

Read Explanation:

M1 D1 H1 = M2 D2 H2 D2 = (M1 D1 H1) / (M2 H2) = (5 x 7 x 4) / (1 x 10) = 14days


Related Questions:

സന്ധ്യ ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ഗോപു അതു ചെയ്യാൻ 60 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടു പേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
Two pipes A and B can fill a cistern in 36 minutes and 48 minutes, respectively. Both the pipes are opened at the same time and pipe B is closed after some time. If the cistern gets filled in half an hour, then after how many minutes was pipe B closed?
A bicycle is sold at a profit of 10%. Had it been sold for 900 less, there would have been a loss of 10%. The cost price of the bicycle is:
6/7 part of a tank is filled with oil. After taking out 60 litres of oil the tank is 4/5 part full. What is the capacity (in litres) of the tank?
Ratul can do a piece of work in 24 days and Amal can do the same work in 32 days. They worked together for 8 days and then Amal left. How much time (in days ) will Ratul, working alone, take to complete the remaining work?