In an MRP system, component demand is
AForecasted
BEstablished by the master production schedule
CCalculated by the MRP system from the master production schedule
DIgnored
AForecasted
BEstablished by the master production schedule
CCalculated by the MRP system from the master production schedule
DIgnored