In an MRP system, component demand is

AForecasted

BEstablished by the master production schedule

CCalculated by the MRP system from the master production schedule

DIgnored

Answer:

C. Calculated by the MRP system from the master production schedule

Read Explanation:

In an MRP system, component demand is calculated from the master production schedule. This ensures that the materials required for production are accurately determined based on the planned production activities. By relying on the master production schedule, the MRP system can effectively manage inventory levels and production timelines.