In production planning and control, Sequencing problem can be solved using -

AGantt chart

BOnly Delphi method

CBoth Break even point and Delphi method

DOnly Break even point

Answer:

A. Gantt chart

Read Explanation:

Sequencing in production planning and control can be solved by using Gantt charts, which allocate resources to activities and provide a visual display of the project's progress, timelines, dependencies, and phases. Other sequencing methods include Shortest Processing Time, First Come First Serve, Earliest Due Date, and Critical Ratio.


Related Questions:

Which of the following is best fit for analyzing the effect of variable, relationship and manipulation of a model?
In P - system of inventory control -
Which of the following condition reduces the production cost of material per unit?
As opposed to detailed transaction information, the MIS responds to the need for
The amount of time elapsed from the moment an inventory replenishment order is placed and the moment the supplier delivers the goods is