Materials Requirement Planning is driven by

AMaster Production Schedule

Btotal quality measurement

Coverall production planning

Doverall inventory planning

Answer:

A. Master Production Schedule

Read Explanation:

Materials Requirement Planning (MRP) is a crucial component in manufacturing and production management. It is primarily driven by a detailed schedule that outlines the specific products to be produced, the quantities required, and the timeline for production. This schedule ensures that materials are available for production at the right time, minimizing inventory costs and optimizing production efficiency.