Materials requirements planning is driven by

Amaster production schedule

Btotal quality measurement

Coverall production planning

Doverall inventory planning

Answer:

A. master production schedule

Read Explanation:

Material Requirement Planning (MRP) is a method used to ensure that all necessary materials and sub-assemblies are available at the appropriate time for production. The Master Production Schedule (MPS) is a complete timetable of scheduled production that drives MRP. The Inventory Record File provides up-to-date inventory information, while the Bill of Material specifies how each final product is manufactured.