App Logo

No.1 PSC Learning App

1M+ Downloads
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?

A9 days

B14 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Solution:

Given:

P alone can complete a work in 16 days

Q alone can complete the same work in 20 days

P and Q start the work together but Q leaves the work 7 days before the completion of work

Formula used:

Number of days = Total work/1 day's work

Calculation:

P → 16 days

Q → 20 days

Total work = LCM (20, 16) = 80 unit

1 day work of P = 80/16 = 5 unit

1 day work of Q = 80/20 = 4 unit

Now,

P and Q start the work together but Q leaves the work 7 days before the completion of work

(P + Q)'s one day's work = 5 + 4 = 9 unit

Let number of days to complete the Total work be x

⇒ (9 × (x - 7)) + (5 × 7) = 80

⇒ (9x - 63) + 35 = 80

⇒ 9x = 108

∴ x= 108/9 = 12

In 12 days the total work will be completed.

Alternate method:

image.png

According to the question,

P and Q start the work together but Q leaves the work 7 days before the completion of work

Q work complete in 7 days = 4 × 7 = 28 unit

It means 28 unit work by P

Total work done by P and Q

⇒ Total work/efficiency per day both

⇒ (80 + 28)/(5 + 4)

⇒ 108/9 = 12 days

 In 12 days the total work will be completed.


Related Questions:

In a box there are 16 white socks and 12 black socks. A person picked socks with closed eye. The minimum number of socks that he has to pick to get a pair?
54kg ധാന്യം 35 കുതിരകൾക്ക് 21 ദിവസത്തേക്ക് തികയുമെങ്കിൽ 72kg ധാന്യം 28 കുതിരകൾക്ക് എത്ര ദിവസത്തേക്ക് തികയും?
E and F can do a work in 10 days. If E alone can do it in 30 days, F alone can do it in ____ days.
60 men can complete a work in 40 days. They start work together but after every 10 day, 5 men leave the work. In how many days will the work be completed?
A, B and C together can build a wall in 12 days. C is four times as productive as B and A alone can build the wall in 48 days. In how many days A and B working together can build the wall?