App Logo

No.1 PSC Learning App

1M+ Downloads
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?

A9 days

B14 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Solution:

Given:

P alone can complete a work in 16 days

Q alone can complete the same work in 20 days

P and Q start the work together but Q leaves the work 7 days before the completion of work

Formula used:

Number of days = Total work/1 day's work

Calculation:

P → 16 days

Q → 20 days

Total work = LCM (20, 16) = 80 unit

1 day work of P = 80/16 = 5 unit

1 day work of Q = 80/20 = 4 unit

Now,

P and Q start the work together but Q leaves the work 7 days before the completion of work

(P + Q)'s one day's work = 5 + 4 = 9 unit

Let number of days to complete the Total work be x

⇒ (9 × (x - 7)) + (5 × 7) = 80

⇒ (9x - 63) + 35 = 80

⇒ 9x = 108

∴ x= 108/9 = 12

In 12 days the total work will be completed.

Alternate method:

image.png

According to the question,

P and Q start the work together but Q leaves the work 7 days before the completion of work

Q work complete in 7 days = 4 × 7 = 28 unit

It means 28 unit work by P

Total work done by P and Q

⇒ Total work/efficiency per day both

⇒ (80 + 28)/(5 + 4)

⇒ 108/9 = 12 days

 In 12 days the total work will be completed.


Related Questions:

A,B പൈപ്പുകൾ യഥാക്രമം 15 മണിക്കൂറും 18 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് ശൂന്യമാക്കാൻ കഴിയും. പൈപ്പ് C 6 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയ്ക്കാൻ കഴിയും. മൂന്ന് പൈപ്പുകളും ഒരുമിച്ച് തുറന്നാൽ എത്ര കൊണ്ട് ടാങ്കിന്റെ മൂന്നിൽ രണ്ട് ഭാഗം നിറയും?
A can do a certain work in 18 days. B is 25% less efficient than A. A alone worked for a few days and then, B joined him. Both worked together till the completion of the work. The entire work got completed in 12 days. For how many days did A and B work together?
Madhu and Shiney together can complete a piece of work in 20 days, Shiney and Rosy together can complete the same work in 12 days, and Rosy and Madhu together can complete the work in 15 days. In how many days will three of them complete it together?
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?
അജിത്തും സൽമാനും ഒരു ജോലിയുടെ 20% ആദ്യ 3 ദിവസം ചെയ്യുന്നു. പിന്നീട് ചില ശാരീരിക പ്രശ്‌നങ്ങൾ കാരണം അജിത്ത് ജോലി നിർത്തി പോകുന്നു . പിന്നെ സൽമാൻ മാത്രം ബാക്കിയുള്ള ജോലികൾ 20 ദിവസം കൊണ്ട് തീർക്കുന്നു. മുഴുവൻ ജോലിയും ചെയ്യാൻ അജിത്ത് മാത്രം എത്ര ദിവസം എടുക്കും?