App Logo

No.1 PSC Learning App

1M+ Downloads
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?

A9 days

B14 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Solution:

Given:

P alone can complete a work in 16 days

Q alone can complete the same work in 20 days

P and Q start the work together but Q leaves the work 7 days before the completion of work

Formula used:

Number of days = Total work/1 day's work

Calculation:

P → 16 days

Q → 20 days

Total work = LCM (20, 16) = 80 unit

1 day work of P = 80/16 = 5 unit

1 day work of Q = 80/20 = 4 unit

Now,

P and Q start the work together but Q leaves the work 7 days before the completion of work

(P + Q)'s one day's work = 5 + 4 = 9 unit

Let number of days to complete the Total work be x

⇒ (9 × (x - 7)) + (5 × 7) = 80

⇒ (9x - 63) + 35 = 80

⇒ 9x = 108

∴ x= 108/9 = 12

In 12 days the total work will be completed.

Alternate method:

image.png

According to the question,

P and Q start the work together but Q leaves the work 7 days before the completion of work

Q work complete in 7 days = 4 × 7 = 28 unit

It means 28 unit work by P

Total work done by P and Q

⇒ Total work/efficiency per day both

⇒ (80 + 28)/(5 + 4)

⇒ 108/9 = 12 days

 In 12 days the total work will be completed.


Related Questions:

If A can complete a job in 15 days and B can complete the same job in 20 days, then how many days (rounded up to the nearest two decimal places) will it take for both A and B to complete the job together?
'A' യും 'B' യും കൂടി 18 ദിവസങ്ങൾ കൊണ്ട് തീർക്കുന്ന ഒരു ജോലി 'B' യും 'C' യും കൂടി 24 ദിവസങ്ങൾ കൊണ്ടും 'A' യും 'C' യും കൂടി 36 ദിവസങ്ങൾ കൊണ്ടുംതീർക്കും. എങ്കിൽ, 'C' ഒറ്റയ്ക്ക് ഈ ജോലി തീർക്കാൻ എത്ര ദിവസങ്ങൾ എടുക്കും?
The efficiency of A, B, and C is 2 : 3 : 5. A alone can complete a work in 50 days. They all work together for 5 days and then C left the work, in how many days A and B together can complete the remaining work?
30 പേർ ചേർന്ന് 8 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 40 പേർ ചേർന്ന് എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
A and B together can complete a work in 8 days. B alone can complete the work in 24 days. In how many days A alone can complete the same work?