Challenger App

No.1 PSC Learning App

1M+ Downloads
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?

A9 days

B14 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Solution:

Given:

P alone can complete a work in 16 days

Q alone can complete the same work in 20 days

P and Q start the work together but Q leaves the work 7 days before the completion of work

Formula used:

Number of days = Total work/1 day's work

Calculation:

P → 16 days

Q → 20 days

Total work = LCM (20, 16) = 80 unit

1 day work of P = 80/16 = 5 unit

1 day work of Q = 80/20 = 4 unit

Now,

P and Q start the work together but Q leaves the work 7 days before the completion of work

(P + Q)'s one day's work = 5 + 4 = 9 unit

Let number of days to complete the Total work be x

⇒ (9 × (x - 7)) + (5 × 7) = 80

⇒ (9x - 63) + 35 = 80

⇒ 9x = 108

∴ x= 108/9 = 12

In 12 days the total work will be completed.

Alternate method:

image.png

According to the question,

P and Q start the work together but Q leaves the work 7 days before the completion of work

Q work complete in 7 days = 4 × 7 = 28 unit

It means 28 unit work by P

Total work done by P and Q

⇒ Total work/efficiency per day both

⇒ (80 + 28)/(5 + 4)

⇒ 108/9 = 12 days

 In 12 days the total work will be completed.


Related Questions:

A can finish 80% of a task in 12 days and B can finish 20% of the same task in 2 days. They started the task together, but B left after 2 days and A continued to work. In how many days was the entire task completed?
If John can complete a job in 8 hours and Sara can complete the same job in 12 hours how long will it take them to complete the job together ?
Pipes A, B and C can fill a tank in 15, 30 and 40 hours, respectively. Pipes A, B and C are opened at 6 a.m., 8 a.m. and 10 a.m., respectively, on the same day. When will the tank be full?
2 പുരുഷന്മാർക്കും 3 സ്ത്രീകൾക്കും 6 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, 3 പുരുഷന്മാർക്കും 9 സ്ത്രീകൾക്കും 3 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. 12 സ്ത്രീകൾ ചെയ്യുന്ന അതേ ജോലി ചെയ്യാൻ, എത്ര പുരുഷന്മാർ ആവശ്യമാണ്?
രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 12 മണിക്കൂറും 15 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും 4 മണിക്കൂർ തുറന്നു ആദ്യത്തെ പൈപ്പ് അടച്ചാൽ, ശേഷിക്കുന്ന ടാങ്ക് നിറയ്ക്കാൻ രണ്ടാമത്തെ പൈപ്പ് എടുക്കുന്ന സമയം കണ്ടെത്തുക