App Logo

No.1 PSC Learning App

1M+ Downloads
P alone can complete a work in 16 days and Q alone can complete the same work in 20 days. P and Q start the work together but Q leaves the work 7 days before the completion of work. In how many days the total work will be completed?

A9 days

B14 days

C12 days

D18 days

Answer:

C. 12 days

Read Explanation:

Solution:

Given:

P alone can complete a work in 16 days

Q alone can complete the same work in 20 days

P and Q start the work together but Q leaves the work 7 days before the completion of work

Formula used:

Number of days = Total work/1 day's work

Calculation:

P → 16 days

Q → 20 days

Total work = LCM (20, 16) = 80 unit

1 day work of P = 80/16 = 5 unit

1 day work of Q = 80/20 = 4 unit

Now,

P and Q start the work together but Q leaves the work 7 days before the completion of work

(P + Q)'s one day's work = 5 + 4 = 9 unit

Let number of days to complete the Total work be x

⇒ (9 × (x - 7)) + (5 × 7) = 80

⇒ (9x - 63) + 35 = 80

⇒ 9x = 108

∴ x= 108/9 = 12

In 12 days the total work will be completed.

Alternate method:

image.png

According to the question,

P and Q start the work together but Q leaves the work 7 days before the completion of work

Q work complete in 7 days = 4 × 7 = 28 unit

It means 28 unit work by P

Total work done by P and Q

⇒ Total work/efficiency per day both

⇒ (80 + 28)/(5 + 4)

⇒ 108/9 = 12 days

 In 12 days the total work will be completed.


Related Questions:

A,B,C എന്നീ മൂന്ന് പൈപ്പുകൾക്ക് യഥാക്രമം 10, 15, 30 മണിക്കൂർ കൊണ്ട് ഒരു വാട്ടർ ടാങ്ക് ശൂന്യമാക്കാൻ കഴിയും. മൂന്ന് പൈപ്പുകളും ഒരേസമയം തുറന്നാൽ, ടാങ്ക് ശൂന്യമാക്കാൻ എത്ര സമയം (മണിക്കൂറുകൾ) എടുക്കും?
Two pipes A and B can fill a tank in 15 hours and 20 hours, respectively, while a third pipe C can empty the full tank in 30 hours. If all the three pipes operate simultaneously, in how much time will the tank, initially empty, be filled?
A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
18 പേർ 28 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി 24 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ എത ജോലിക്കാർ വേണം?
Harry and Larry can together plough the field in 5 days. Harry alone takes 8 days to plough the same field. In how many days can Larry alone plough the field?