P’s 1-day work = ( \frac{1}{28} )
Q’s 1-day work = ( \frac{1}{35} )
They work alternatively, starting with P.
Work done in 2 days (P + Q):
281+351
=1405+4
=1409
Total work:
In 2 days → <b>(1409)</b>workisdone.
So, in 30 days (15 cycles):
15×1409=140135
Remaining work:
1−140135=1405=281
Day 31:
Next turn is P, and P can complete ( \frac{1}{28} ) in 1 day.
So remaining work is finished on this day.
Final Answer:
31 days