Challenger App

No.1 PSC Learning App

1M+ Downloads
P and Q can complete a piece of work in 28 days and 35 days, respectively. P begins to do the work and they work alternatively one at a time for one day each. In how many days will the whole work be completed?

A31

B27

C18

D21

Answer:

A. 31

Read Explanation:

P’s 1-day work = ( \frac{1}{28} )
Q’s 1-day work = ( \frac{1}{35} )

They work alternatively, starting with P.

Work done in 2 days (P + Q):

128+135\frac{1}{28} + \frac{1}{35}
=5+4140= \frac{5 + 4}{140}
=9140= \frac{9}{140}

Total work:

In 2 days → <b>(9140)</b>workisdone.<b>( \frac{9}{140} )</b> work is done.

So, in 30 days (15 cycles):

15×9140=13514015 \times \frac{9}{140} = \frac{135}{140}

Remaining work:

1135140=5140=1281 - \frac{135}{140} = \frac{5}{140} = \frac{1}{28}

Day 31:

Next turn is P, and P can complete ( \frac{1}{28} ) in 1 day.

So remaining work is finished on this day.

Final Answer:

31 days


Related Questions:

A,B,C എന്നിവ ഒരുമിച്ച് പ്രവർത്തിക്കുമ്പോൾ അവർ 8 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. A,B ഒരുമിച്ച് ജോലി ചെയ്യാൻ തീരുമാനിച്ചപ്പോൾ അവർ 12 ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കി. C ക്കു മാത്രം എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാക്കാൻ കഴിയും?
60 ആളുകൾ 10 ദിവസം കൊണ്ട് തീർക്കുന്ന ജോലി 6 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര ആളുകൾ അധികം വേണ്ടിവരും ?
ഒരു ജോലി 8 പുരുഷന്മാരോ 12 സ്ത്രീകളോ 25 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ കഴിയുമെങ്കിൽ ,10 പുരുഷന്മാരും 5 സ്ത്രീകളും എത്ര ദിവസത്തിനുള്ളിൽ അതേ ജോലി പൂർത്തിയാക്കും ?
A and B can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days beginning with A, then in how many days will the work be completed?
A juice vendor mixes water with pure orange juice. If he sells the mixture at the cost price of pure orange juice and makes a profit of 20%, what is the ratio of water to pure orange juice in the mixture, respectively?