Challenger App

No.1 PSC Learning App

1M+ Downloads
P and Q can complete a piece of work in 28 days and 35 days, respectively. P begins to do the work and they work alternatively one at a time for one day each. In how many days will the whole work be completed?

A31

B27

C18

D21

Answer:

A. 31

Read Explanation:

P’s 1-day work = ( \frac{1}{28} )
Q’s 1-day work = ( \frac{1}{35} )

They work alternatively, starting with P.

Work done in 2 days (P + Q):

128+135\frac{1}{28} + \frac{1}{35}
=5+4140= \frac{5 + 4}{140}
=9140= \frac{9}{140}

Total work:

In 2 days → <b>(9140)</b>workisdone.<b>( \frac{9}{140} )</b> work is done.

So, in 30 days (15 cycles):

15×9140=13514015 \times \frac{9}{140} = \frac{135}{140}

Remaining work:

1135140=5140=1281 - \frac{135}{140} = \frac{5}{140} = \frac{1}{28}

Day 31:

Next turn is P, and P can complete ( \frac{1}{28} ) in 1 day.

So remaining work is finished on this day.

Final Answer:

31 days


Related Questions:

ഒരു ജോലി ചെയ്തുതീർക്കാൻ ബാലു തനിച്ച് ചെയ്താൽ 10 ദിവസവും രാമു തനിച്ച് ചെയ്താൽ 15 ദിവസവും വേണം രാമുവും ബാലുവും ജോലി ചെയ്താൽ എത്ര ദിവസം കൊണ്ട് ആ ജോലി തീർക്കാം ?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
5 men and 6 women can do a piece of work in 6 days while 3 men and 5 women can do the same work in 9 days. In how many days can 3 men and 2 women do the same work?
ജോണിക്ക് 40 ദിവസം കൊണ്ടും രാജുവിന് 48 ദിവസം കൊണ്ടും ബോബിക്ക് 60 ദിവസം കൊണ്ടും ഒരു ജോലി തീർക്കാൻ കഴിയും. അവർ 4 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്തു. തുടർന്ന് രാജു പോയി. അതിനുശേഷം ജോണിയും ബോബിയും 12 ദിവസം ഒരുമിച്ച് ജോലി ചെയ്ത ശേഷം ജോണി പോയി. ബോബിയുടെ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസമെടുക്കും ?
The speed of a stream is 9 km/h. A boat can go 56 km downstream and 28 km upstream in 7 hours. What is the speed (in km/h) of the boat in still water?