PERT stands for

AProgramme Estimation and Reporting Technique

BProcess Estimation and Review technique

CProgramme Evaluation and Review Technique

DProcess Evaluation and Reporting Technique

Answer:

C. Programme Evaluation and Review Technique


Related Questions:

When the expenditure of a work exceeds or likely to exceed the amount of sanctioned estimate by more than 10%, then the prepared detailed estimate is known as:
While submitting tender the contractor is to deposit 2% of estimated cost as
The post-operation in CPM are marked:
The main factor to be considered while preparing a detailed estimate is:
In critical path method the performance of a specific task is called