Consider the following statements in respect of PERT and CPM: Which of the statements are correct?
- PERT is event-oriented while CPM is activity-oriented.
- PERT is probabilistic while CPM is deterministic.
- Levelling and smoothing are the techniques related to resource scheduling in CPM.
Aii only
BNone of these
Cii, iii
DAll of these