App Logo

No.1 PSC Learning App

1M+ Downloads

Consider the following statements in respect of PERT and CPM: Which of the statements are correct?

  1. PERT is event-oriented while CPM is activity-oriented.
  2. PERT is probabilistic while CPM is deterministic.
  3. Levelling and smoothing are the techniques related to resource scheduling in CPM.

    Aii only

    BNone of these

    Cii, iii

    DAll of these

    Answer:

    D. All of these

    Read Explanation:

    image.png

    Related Questions:

    The simplex method is used for solving ________________________problems.
    The _________________path within a network diagram is called critical path.
    Positive slack in PERT indicates
    A variable that has no physical meaning, but is used to obtain an initial basic feasible solution to the linear programming problem is referred to as:
    In PERT analysis, the possible number of time estimates for activities linking up two events are -