App Logo

No.1 PSC Learning App

1M+ Downloads

A can do 15\frac{1}{5}th of a work in 4 days and B can do 16\frac{1}{6}th of the same work in 5 days. In how many days they can finish the work, if they work together?

A12

B20

C15

D30

Answer:

A. 12

Read Explanation:

Solution;

A can do 15\frac{1}{5}th work in 4days.

Efficiency of A = 14×5=120\frac{1}{4\times5}=\frac{1}{20}

B can do 16\frac{1}{6}th of the work in 5days.

Efficiency of B = 16×5=130\frac{1}{6\times5}=\frac{1}{30}

Combined Efficiency of A and B is = 120+130\frac{1}{20}+\frac{1}{30}

=3+260=560=112=\frac{3+2}{60}=\frac{5}{60}=\frac{1}{12}

A and B together can complete the work in 12 days.

Shortcut:

image.png

A can do 1/5th of a work in = 4 days

A can do the whole work in = 4×5=20days4\times 5 = 20 days

B can do 1/6th of the same work in = 5 days

B can do the whole work in = 5×6=30days5 \times 6 = 30 days

From the following figure

Total work = 60

Total efficiency of A and B = 2 + 3 = 5

A and B together can complete the whole work in = 605=12days\frac{60}{5} = 12 days


Related Questions:

A,B,C എന്നിവ ഒരുമിച്ച് പ്രവർത്തിക്കുമ്പോൾ അവർ 8 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കും. A,B ഒരുമിച്ച് ജോലി ചെയ്യാൻ തീരുമാനിച്ചപ്പോൾ അവർ 12 ദിവസം കൊണ്ട് ഈ ജോലി പൂർത്തിയാക്കി. C ക്കു മാത്രം എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാക്കാൻ കഴിയും?
A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, then B left the work. In how many days will A alone complete 60% of the remaining work?
A and B working separately can finish a work in 15 days and 20 days. respectively. If they work on alternate days. A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?
10 ആളുകൾക്ക് ഒരു ജോലി ചെയ്യാൻ 8 ദിവസം വേണം. അതേ ജോലി ചെയ്യാൻ 20 ആളുകൾക്ക് എത്ര ദിവസം വേണം ?