The amount to be spent for the completion of unit quantity of a particular work, is

ACost

BRate

CEstimate

DExpense

Answer:

B. Rate


Related Questions:

Face left and face right observations eliminate the error
Permanent adjustment are carried out to
Which of the following is an antifriction bearing
In a whole circle bearing System, S 25° 25' E corresponding to
The effective length of a fillet weld is