App Logo

No.1 PSC Learning App

1M+ Downloads
The drawing essentially to be entered with the preliminary estimate:

ASite plan and detailed plan of building

BSite plan and line plan of the building

CNo drawings needed

DDetailed drawing of the building only

Answer:

B. Site plan and line plan of the building


Related Questions:

The amount shown in the account book after allowing necessary depreciation is:
The capacity of doing work by a skilled labour, is the form of quantity of work per day is known as:
The fresh detailed estimate of the additional work in addition to the original when further development is required during the progress of the work
The time by which a particular activity may be delayed without affecting the preceeding and succeeding activities is known as:
A property through physically sound, but it becomes out of date in style, structure in design and thus it loses its functional utility, this is: