App Logo

No.1 PSC Learning App

1M+ Downloads
The initial lead and lift of earth work excavation in ordinary soil and depositing the earth on bank is

A100 m and 1 m

B50 m and 1.5 m

C200 m and 2 m

D75 m and 0.90 m

Answer:

B. 50 m and 1.5 m


Related Questions:

Driving a steel rod or iron pipe in soil to ascertain the soil conditions is called ____________________ method of site exploration
The deflection at any section of a beam is ...... of the corresponding section of the conjugate beam
A shaft whose upper deviation is zero is called basic shaft. Which one of the following letters indicates basic shaft?
The tendency of the mineral to split along a certain plane is called:
The external curve of the arch is known as: