The process of fixing the sequence of operations and material flow is

AMaster scheduling

BScheduling

CExpediting

DRouting

Answer:

D. Routing

Read Explanation:

Routing is the process of fixing the sequence of operations and material flow in manufacturing. It determines the path and order in which work will be performed.