The rise and fall method of levelling is :

ALess accurate than height of instrument method

BIs not suitable for levelling with tilting levels

CQuicker and less tedious for large number of intermediate sight

DProvides a check on the reduction of intermediate point levels

Answer:

D. Provides a check on the reduction of intermediate point levels