The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the engineering department is called:

ADepartment sanction

BAdministrative sanction

CTechnical sanction

DExpenditure sanction

Answer:

C. Technical sanction