Unit of stone masonry

Am

B10 m^3

Cm^3

Dm^2

Answer:

C. m^3


Related Questions:

Critical path on PERT/CPM chart is obtained by joining the events having :
In the analyses of rates, the provision included, as contractor's profit is:
Work costing less than 20,000 is called:
The Instrument which register the number of paces of the person carrying it:
Pick up the item of work not included in the plinth area estimate