App Logo

No.1 PSC Learning App

1M+ Downloads
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

A3/5

B1/3

C1/2

D2/5

Answer:

D. 2/5

Read Explanation:

Vikram and Vivek can finish a work in = 50 days

1 day work by them = 150\frac{1}{50}

∴ Work done by them in 20 days = 20×(150)=2520\times{(\frac{1}{50})}=\frac{2}{5}


Related Questions:

P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?
Two pipes can fill a tank in 15 hours and 4 hours, respectively, while a third pipe can empty it in 12 hours. How long (in hours) will it take to fill the empty tank if all the three pipes are opened simultaneously?
A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for the first half of the day daily, then in how many days will A and B together complete the work?
ഒരു ജോലി ചെയ്യാൻ, A യും B യും 6780 രൂപ വാങ്ങുന്നു. അവർ ഒരുമിച്ച് പ്രവർത്തിക്കുകയാണെങ്കിൽ അവർ 12 ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കുന്നു, A ഒറ്റയ്ക്ക് ജോലി ചെയ്യുന്നുവെങ്കിൽ അദ്ദേഹം 15 ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കുന്നു. ഇരുവരും ഒരുമിച്ച് പ്രവർത്തിക്കുമ്പോൾ B യുടെ പങ്ക് എന്താണ്?
Rachna can eat 21 oranges in 60 minutes. She wants to know how many minutes it would take her to eat 35 oranges at the same pace?