What is the initial step in the planning phase for a Disaster Management Exercise (DMEx)?

AConstituting the Exercise Management Team.

BFixing Exercise Objectives.

CExercise Proposal and Approval.

DBudget Allocation.

Answer:

C. Exercise Proposal and Approval.

Read Explanation:

This is the very beginning of the entire process. Before any detailed planning can occur, a formal proposal must be drafted to outline the need for the exercise, its high-level objectives, and a preliminary scope. This proposal is then submitted to the appropriate senior leadership or authority for review and approval. Gaining this approval is critical because it:

  • Authorizes the exercise: Gives the green light for the project to proceed.

  • Secures resources: Often includes the initial commitment of a budget and personnel.

  • Establishes official support: Ensures that the exercise has the necessary organizational backing to be successful.


Related Questions:

പുനഃസ്ഥാപിക്കാൻ കഴിയാത്ത ഊർജ്ജ സ്രോതസ്സായ കൽക്കരിയുമായി ബന്ധപ്പെട്ട് താഴെ തന്നിട്ടുള്ള പ്രസ്താവനകളിൽ ശരിയായത് ഏതെല്ലാമാണ് ?

1.ഭൂമിയിൽ നിന്ന് ലഭിക്കുന്ന ഫോസിൽ ഇന്ധനങ്ങളിൽ ഏറ്റവും കൂടുതലുള്ളത് കൽക്കരി ആണ്.

2.കാർബണാണ് കൽക്കരിയിലെ പ്രധാന ഘടകം.

3.ഇന്ത്യയിൽ കൽക്കരി ഉത്പാദനത്തിൽ ഒന്നാം സനത്ത് നിൽക്കുന്ന സംസ്ഥാനം രാജസ്ഥാൻ ആണ്.

നിക്കോ ടിൻബെർഗൻ എഴുതിയ "ദി സ്റ്റഡി ഓഫ് ഇൻസ്റ്റിങ്ക്റ്റ്" എന്ന പുസ്തകം ഏത് വർഷമാണ് പ്രസിദ്ധീകരിച്ചത്?

Consider the following statements regarding floods and flash floods.

  1. All floods are specifically defined as occurring within six hours of heavy rainfall.
  2. Flash floods are a specific type of flood characterized by rapid onset and swift water flow.
  3. An increase in reservoir levels can lead to a general flood, but not a flash flood.
    What does the following diagram indicate?

    Which of the following statements about establishing and maintaining coordination in disaster management are correct?

    1. Systematic coordination is crucial among all relevant governmental and non-governmental institutions.
    2. Only governmental agencies are required to participate in disaster coordination efforts.
    3. Establishing coordination helps in streamlining disaster response and recovery.
    4. Coordination plans are primarily designed for post-disaster evaluation, not immediate response.