What is the step immediately following the 'Exercise Proposal and Approval' in the DMEx planning phase?

APreparing the Exercise Scenario and Narrative.

BConstituting the Exercise Management Team.

CDeciding Participation and Event Schedule.

DIssuing a Concept Note.

Answer:

B. Constituting the Exercise Management Team.

Read Explanation:

Once the exercise has received official authorization and a general budget, the next logical and immediate step is to establish the core group responsible for its detailed planning and execution. The EMT is a dedicated team of individuals with the authority and expertise to manage all aspects of the DMEx, from scenario development to final reporting. Forming this team early ensures a clear command structure and accountability for every subsequent task in the planning phase.


Related Questions:

Regarding the causes and prevalence of droughts, which statement(s) is/are correct?

  1. Droughts are exclusively limited to tropical rainforest regions.
  2. Inadequate water management practices and governmental oversight can contribute to the occurrence of droughts.
  3. While severe droughts can occur anywhere, they are particularly prevalent in arid and semi-arid zones.

    Which act does the NPDM 2009 align with and build upon?

    1. The NPDM was created to align with and build upon the Disaster Management Act of 2005.
    2. The NPDM aligns with the Environment Protection Act of 1986.
    3. The NPDM is independent of any previous legislation.
      Which of the following is NOT listed as a crucial role of Discussion-Based DMEx?
      ഇന്ത്യയിൽ വന്യജീവി സംരക്ഷണ നിയമം നടപ്പിലാക്കിയത് ഏത് വർഷമാണ്?
      What is the primary aim of the preparatory work for Community Based Disaster Management (CBDM) plans?