Which among the following is the lowermost portion of a foundation which is in direct contact with the subsoil

APlinth

BFooting

CBoth A and B

DNone of these

Answer:

B. Footing


Related Questions:

Weirs constructed on permeable foundation are Likely to fail due to:
The height of arch ring from the centre of springing line is called
In brick masonry, the type of bond in which alternate courses of stretchers and headers are laid with queen closer after the first header is
Joints not used in the stone masonry are
Spread footing is otherwise called