App Logo

No.1 PSC Learning App

1M+ Downloads
Which of the following is a PERT event:

ATransport of sand

BTransport of cement

CConcreting of roof completed

DMaking of formwork continues

Answer:

A. Transport of sand


Related Questions:

The sanction of the detailed estimate, design calculations, quantities of works, rates and cost of the work by the competent authority of the engineering department is called:
For compacting the quantity of earthwork using prismoidal formula the number of required sectional area
The most reliable estimate is:
The time corresponding to minimum total project cost is:
PERT stands for :