Which of the following is the correct process sequence of conducting a Green Audit?

AReport → Data collection → Site visit → Analysis → Recommendations

BSite visit → Pre-audit planning → Recommendations → Report → Analysis

CPre-audit planning → Site visit → Data collection → Analysis → Report → Recommendations

DAnalysis → Data collection → Report → Planning

Answer:

C. Pre-audit planning → Site visit → Data collection → Analysis → Report → Recommendations

Read Explanation:

  • The correct systematic process is: Pre-audit planning → Site visit → Data collection → Analysis → Report → Recommendations.