App Logo

No.1 PSC Learning App

1M+ Downloads
Which of the following statement/statements is/are correct?

APERT considers activity time as a random variable

BCPM considers a single deterministic time value for the activities

CCPM considers trade-off between time and cost

DAll of the above

Answer:

D. All of the above

Read Explanation:

CPM considers a fixed time estimate for each activity and focuses on trade-offs between time and cost. PERT, on the other hand, is a stochastic model that considers uncertainty in activity completion time and allows for randomness PERT includes three-time estimates for each activity optimistic time, pessimistic time, and most likely time.


Related Questions:

The _________________path within a network diagram is called critical path.
Which of the following is NOT a direct cost?
Which of the following is NOT correct critical path method (CPM) used in Project scheduling?
Variables used in the objective function while solving linear programming problems are known as__________________ variables.
While solving a linear programming model, if a redundant constraint is added, then what will be its effect on existing solution?