Which of the statements given below is not correct: When there is a dispute in a construction site,

AThe dispute must be submitted initially to the site Engineer for decision, before referring to arbitration

BThe contractor has to stop the work till the settlement of dispute

CAll actions related thereto should be recorded and referred for future negotiations and agreements

DA meeting must be held between the superintendent and union leader

Answer:

B. The contractor has to stop the work till the settlement of dispute