Which one of the following is Not a decision taken during the aggregate production planning stage?

AScheduling of machines

BAmount of labour to be committed

CRate at which production should happen

DInventory to be carried forward

Answer:

A. Scheduling of machines

Read Explanation:

Aggregate production planning is a capacity planning process that balances supply and demand for a period of fewer than 18 months. It establishes employment levels, output rates, inventory levels, subcontracting, and backorders for products that are aggregated. The decision of scheduling machines is not taken during this stage.


Related Questions:

Which of the following is an example of flow production?
Which one of the following is correct? Production, planning and control functions are extremely complex in
The difference between actual sales and breakeven point is known as

If an object is being painted while transported by chain conveyor can be shown by symbol

image.png
During manufacture of cement, the handling of lime stone