X and Y can complete a piece of work in 8 days and 12 days, repectively. If they work on alternate days, with X working on the first day , how long will it take the duo to complete the same work?

A925days9\frac{2}{5}days

B935days9\frac{3}{5}days

C923days9\frac{2}{3}days

D912days9\frac{1}{2}days

Answer:

912days9\frac{1}{2}days

Read Explanation:

X can do the work in 8 days

Y can do the work in 12 days

LCM of 8 , 12 is 24

Total work =24

.Efiiciency of X = 248=3\frac{24}{8}=3

Efficiency of Y = 2412=2\frac{24}{12}=2

Working on alternate days start with X

3+2 = 5 work done on 2days

in 4days 10 work done

in 6 days 15 work done

in 8days 20 work done

in 9days 23 work done

Remaining 1 work done by Y

9+12=912days9+\frac{1}{2}=9\frac{1}{2}days


Related Questions:

A and B working separately can finish a work in 15 days and 20 days. respectively. If they work on alternate days. A starting first, and if the work goes on for 8 days, what part of the work will be left unfinished?
ഒരു പൈപ്പിന് മറ്റൊരു പൈപ്പിനേക്കാൾ മൂന്നിരട്ടി വേഗത്തിൽ ടാങ്കിൽ നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും ചേർന്ന് 36 മിനിറ്റിനുള്ളിൽ ടാങ്ക് നിറയ്ക്കാൻ കഴിയുമെങ്കിൽ, വേഗത കുറഞ്ഞ പൈപ്പിന് എത്ര നേരം കൊണ്ട് ടാങ്ക് നിറക്കാം?
Anil can do a piece of work in 4 hours. Ashok can do it in 8 hours. With the assistance of Robin, they completed the work in 2 hours. In how many hours can Robin alone do it?
A can do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
400 തൊഴിലാളികൾക്ക് 75 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അതിൽ നിന്ന് 25 തൊഴിലാളികളെ മാറ്റിയാൽ ആ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസം വേണ്ടിവരും ?