X takes twice as much time as Y or thrice as much time as Z to finish a job. Working together, the trio can finish the job in 2 days. Y alone can do the work in ______.

A6

B12

C18

D15

Answer:

A. 6

Read Explanation:

Solution: Given: Time taken by X = 2 × Time taken by Y Time taken by X = 3 × Time taken by Z Time to complete work together = 2 days Concept used: Efficiency to do a work is inversely proportional to time taken for the same. Total work = Time × Efficiency Calculation: According to the question, Time ratio, X : Y : Z = 6 : 3 : 2 So, Efficiency ratio = 1/6 : 1/3 : 1/2 Multiply each term by 6 ⇒ Efficiency ratio = 6/6 : 6/3 : 6/2 = 1 : 2 : 3 Combined efficiency = 6 units So, total work = 6 units × 2 = 12 units Efficiency 'of Y = 2 units So, time taken by Y alone to do the work = 12/2 = 6 days ∴ Y will finish the work alone in 6 days.


Related Questions:

A tank is filled in 4 hours by three pipes A, B and C. Pipe C is twice as fast as pipe B and pipe B is twice as fast as pipe A. How much time will pipe A take to fill the tank?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
A can do a piece of work in 30 days, while B alone can do it in 40 days. In how many days can A and B working together do it?
ഒരു ടാങ്കിൽ വെള്ളം വരുന്ന രണ്ട് പൈപ്പുകൾ ഉണ്ട്. അവയിൽ ഒരു പൈപ്പ് തുറന്നാൽ 5 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും. മറ്റേതു തുറന്നാൽ 3 മണിക്കൂർ കൊണ്ട് ടാങ്ക് നിറയും. രണ്ടു പൈപ്പുകളും ഒരുമിച്ച് തുറന്നിട്ടാൽ എത്ര മണിക്കൂർകൊണ്ട് ടാങ്ക് നിറയും ?
15 പേർ 8 ദിവസം കൊണ്ട് 40 പാവ ഉണ്ടാക്കുന്നു.3 പേർ ജോലി ഉപേക്ഷിച്ചു പോയാൽ 48 പാവ ഉണ്ടാക്കാൻ എത്ര ദിവസം വേണം ?