X takes twice as much time as Y or thrice as much time as Z to finish a job. Working together, the trio can finish the job in 2 days. Y alone can do the work in ______.

A6

B12

C18

D15

Answer:

A. 6

Read Explanation:

Solution: Given: Time taken by X = 2 × Time taken by Y Time taken by X = 3 × Time taken by Z Time to complete work together = 2 days Concept used: Efficiency to do a work is inversely proportional to time taken for the same. Total work = Time × Efficiency Calculation: According to the question, Time ratio, X : Y : Z = 6 : 3 : 2 So, Efficiency ratio = 1/6 : 1/3 : 1/2 Multiply each term by 6 ⇒ Efficiency ratio = 6/6 : 6/3 : 6/2 = 1 : 2 : 3 Combined efficiency = 6 units So, total work = 6 units × 2 = 12 units Efficiency 'of Y = 2 units So, time taken by Y alone to do the work = 12/2 = 6 days ∴ Y will finish the work alone in 6 days.


Related Questions:

P യും Q വും ചേർന്ന് 12 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്യാൻ കഴിയും, P ക്ക് മാത്രം 15 ദിവസം കൊണ്ട് ചെയ്യാൻ കഴിയും. Q മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ അത് ചെയ്യാൻ കഴിയും?
Manoj can do a piece of work in 8 hours. Anand can do it in 8 hours. With the assistance of Anil, they completed the work in 2 hours. In how many hours can Anil alone do it?
A and B can do a work together in 18 days. A is three times as efficient as B. In how many days can B alone complete the work?
6 ആളുകൾ ഒരു ജോലി 10 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു . എന്നാൽ ഒരാൾ ആ ജോലി എത്ര ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും ?
6 മിനിട്ടുകൊണ്ട് ഒരു ടാങ്കിന്റെ 3/5 ഭാഗം നിറഞ്ഞു. ഇനി നിറയാൻ എത്ര മിനിട്ടു വേണം ?