30 men working 8 hours per day can dig a pond in 16 days. By working how many hours per day can 32 men dig the same pond in 20 days?

A7 hours per day

B5 hours per day

C8 hours per day

D6 hours per day

Answer:

D. 6 hours per day

Read Explanation:

Solution: Given: 30 men working 8 hours per day can dig a pond in = 16 days Formula: M1 × T1 × D1 = M2 × T2 × D2 Calculation: M1 = 30 men, T1 = 8 hrs, D1 = 16 days, M2 = 32 men, D2 = 20 days According to the formula 30 × 8 × 16 = 32 × T2 × 20 ⇒ T2 = (30 × 8 × 16)/(32 × 20) ∴ T2 = 6 hrs.


Related Questions:

A can do 15\frac{1}{5}th of a work in 4 days and B can do 16\frac{1}{6}th of the same work in 5 days. In how many days they can finish the work, if they work together?

Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
Two inlet pipes A and B together can fill a tank in 24 min, and it takes 6 min more when one leak is developed in the tank. Find the time taken by leak alone to empty the tank.
6 പൈപ്പുകൾ ഉപയോഗിച്ച് ഒരു ടാങ്കിൽ വെള്ളം നിറയ്ക്കാൻ 1 മണിക്കൂർ 20 മിനിറ്റ് വേണം . എന്നാൽ അഞ്ചു പൈപ്പുകൾ ഉപയോഗിച്ചാണ് നിറയ്ക്കുന്നത് എങ്കിൽ എത്ര സമയം വേണം ?
P can do a piece of work in 48 days, which Q can do in 18 days. Q worked at it for 15 days. P can finish the remaining work in: