App Logo

No.1 PSC Learning App

1M+ Downloads
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?

A72

B56

C64

D36

Answer:

B. 56

Read Explanation:

Solution: Given: 5 men and 8 women can complete a task = 34 days 4 men and 18 women can complete the same task = 28 days Formula: Total work = Efficiency × Time Calculation: Let efficiency of 1 man and 1 woman be x and y respectively, then (5x + 8y) × 34 = (4x + 18y) × 28 ⇒ (5x + 8y) × 17 = (4x + 18y) 14 ⇒ 85x + 136y = 56x + 252y ⇒ 85x - 56x = 252y - 136y ⇒ 29x = 116y ⇒ x/y = 116/29 ⇒ x : y = 4 : 1 Total work = (5 × 4 + 8 × 1) × 34 Total work = (20 + 8) × 34 Total work = 28 × 34 Efficiency of 3 men and 5 women in 1 day = (3 × 4 + 5 × 1) = 12 + 5 = 17 ∴ Time taken by 3 men and 5 women to complete the whole work = (28 × 34)/17 = 56 days


Related Questions:

A യും B യും ഒരുമിച്ച് 40 ദിവസത്തിനുള്ളിൽ ഒരു ജോലി ചെയ്യുന്നു. B യും C യും ഒരുമിച്ച് 25 ദിവസത്തിനുള്ളിൽ ചെയ്യുന്നു. എയും ബിയും ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, എ 6 ദിവസത്തിന് ശേഷം ജോലി ഉപേക്ഷിച്ചു, ബി 8 ദിവസത്തിന് ശേഷം ജോലി ഉപേക്ഷിച്ചു. A പോയതിനു ശേഷം, C ജോലിയിൽ ചേരുകയും C 40.5 ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കുകയും ചെയ്തു, C-യ്ക്ക് മാത്രം എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കാൻ കഴിയും?
15 പേർ 24 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 18 ദിവസം കൊണ്ട് തീർക്കാൻ എത്ര പേർ വേണം?
One pipe fills a water tank 3 times faster than the other. If the two pipes together can fill the empty tank in 37 minutes, then how much time will the slower pipe alone take to fill the tank?
A, B and C complete a piece of work in 20, 9 and 12 days respectively. Working together, they will complete the same work in
One pipe can fill the tank in 20 min while another pipe can empty it in 60 min. If both the pipes are operated together, how long will it take to fill the tank completely?