App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:

A24 days

B12 days

C20 days

D16 days

Answer:

D. 16 days

Read Explanation:

Solution: Given: Time taken by A to complete the work is 10 days. Time taken by B to complete the work is 15 days. Time taken by C to complete remaining work is 12 days. Concept Used: Time taken = (Total work done)/(Efficiency) Calculation: Let the work done by A, B and C be in Units. Total Work done by (A + B) = L.C.M of (10, 15) ⇒ 30 Units Now, Efficiency of A = Total Work/Time taken ⇒ 30/10 = 3 units per day Efficiency of B = Total Work/Time taken ⇒ 30/15 = 2 units per day Total Work done by (A + B) in 4 days = (Sum of efficiency of A and B) × 4 ⇒ (3 + 2) × 4 = 20 units Remaining Work = (30 - 20) = 10 units Efficiency of C for completing remaining work = 10/12 ⇒ (5/6) unit per day Then, Time taken by C to complete (4/9) part of original work = 30 × (4/9) × (6/5) ⇒ 16 days ∴ Time taken by C to complete (4/9) part of original work is 16 days.


Related Questions:

Jitesh and Kamal can complete a certain piece of work in 18 and 17 days, respectively, They started to work together, and after 5 days, Kamal left. In how many days will Jitesh complete the remaining work?
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed ?
A , B എന്നിവർക്ക് യഥാക്രമം 15 ദിവസവും 10 ദിവസവും ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അവർ ഒരുമിച്ച് ജോലി ചെയ്യാൻ തുടങ്ങി, പക്ഷേ 2 ദിവസത്തിന് ശേഷം Bക്ക് പോകേണ്ടി വന്നു, A മാത്രം ബാക്കിയുള്ള ജോലി പൂർത്തിയാക്കി. A പണി പൂർത്തിയാക്കാൻ എത്ര ദിവസം എടുക്കും?
If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?
A certain number of men complete a piece of work in 60 days. If there were 8 men more, the work could be finished in 10 days less. How many men were originally there?