Challenger App

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:

A24 days

B12 days

C20 days

D16 days

Answer:

D. 16 days

Read Explanation:

Solution: Given: Time taken by A to complete the work is 10 days. Time taken by B to complete the work is 15 days. Time taken by C to complete remaining work is 12 days. Concept Used: Time taken = (Total work done)/(Efficiency) Calculation: Let the work done by A, B and C be in Units. Total Work done by (A + B) = L.C.M of (10, 15) ⇒ 30 Units Now, Efficiency of A = Total Work/Time taken ⇒ 30/10 = 3 units per day Efficiency of B = Total Work/Time taken ⇒ 30/15 = 2 units per day Total Work done by (A + B) in 4 days = (Sum of efficiency of A and B) × 4 ⇒ (3 + 2) × 4 = 20 units Remaining Work = (30 - 20) = 10 units Efficiency of C for completing remaining work = 10/12 ⇒ (5/6) unit per day Then, Time taken by C to complete (4/9) part of original work = 30 × (4/9) × (6/5) ⇒ 16 days ∴ Time taken by C to complete (4/9) part of original work is 16 days.


Related Questions:

ഒരാൾ 12 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി നാല് ആളുകൾ എത്ര ദിവസം കൊണ്ട് ചെയ്തുതീർക്കും?
P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
രാമു ഒരു ജോലി 6 ദിവസം കൊണ്ട് ചെയ്യും. രമ അതേ ജോലി ചെയ്യാൻ 8 ദിവസം എടുക്കും. എന്നാൽ രണ്ടുപേരും ഒരുമിച്ച് ജോലി ചെയ്താൽ ജോലി തീർക്കാൻ എത്ര ദിവസം വേണം ?
A tap can fill a tank in 8 hours. After half the tank is filled, four more similar taps are opened. What is the total time taken to fill the tank completely?
A tank is filled in 4 hours by three pipes A, B and C. Pipe C is twice as fast as pipe B and pipe B is twice as fast as pipe A. How much time will pipe A take to fill the tank?