App Logo

No.1 PSC Learning App

1M+ Downloads
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:

A24 days

B12 days

C20 days

D16 days

Answer:

D. 16 days

Read Explanation:

Solution: Given: Time taken by A to complete the work is 10 days. Time taken by B to complete the work is 15 days. Time taken by C to complete remaining work is 12 days. Concept Used: Time taken = (Total work done)/(Efficiency) Calculation: Let the work done by A, B and C be in Units. Total Work done by (A + B) = L.C.M of (10, 15) ⇒ 30 Units Now, Efficiency of A = Total Work/Time taken ⇒ 30/10 = 3 units per day Efficiency of B = Total Work/Time taken ⇒ 30/15 = 2 units per day Total Work done by (A + B) in 4 days = (Sum of efficiency of A and B) × 4 ⇒ (3 + 2) × 4 = 20 units Remaining Work = (30 - 20) = 10 units Efficiency of C for completing remaining work = 10/12 ⇒ (5/6) unit per day Then, Time taken by C to complete (4/9) part of original work = 30 × (4/9) × (6/5) ⇒ 16 days ∴ Time taken by C to complete (4/9) part of original work is 16 days.


Related Questions:

Jitesh and Kamal can complete a certain piece of work in 7 and 11 days, respectively, They started to work together, and after 3 days, Kamal left. In how many days will Jitesh complete the remaining work?
P, Q, R എന്നിവയ്ക്ക് യഥാക്രമം 8, 16, 24 ദിവസങ്ങളിൽ ഒരു ജോലി ചെയ്യാൻ കഴിയും. എല്ലാവരും ഒരുമിച്ച് ജോലി ആരംഭിച്ചു P മാത്രം ജോലി പൂർത്തിയാകുന്നത് വരെ തുടർന്നു, ആരംഭിച്ചു രണ്ടു ദിവസത്തിനുശേഷം R ഉം ജോലിപൂർത്തിയാകുന്നതിന് ഒരു ദിവസം മുൻപ് Q ഉം പിരിഞ്ഞു പോയി എങ്കിൽ ജോലി പൂർത്തിയാക്കാൻ എടുക്കുന്ന സമയം
image.png
Robert takes twice as much time as Tom and thrice as much time as George to complete a work. If working together, they can complete it in 23 hours, then find the time that Tom will take to complete the work.
"A' ഒരു ജോലി 20 ദിവസം കൊണ്ടും "B' അതേ ജോലി 30 ദിവസം കൊണ്ടും ചെയ്തുതീർക്കും. A യും B യും ഒരുമിച്ച് ആ ജോലി ചെയ്യുകയാണെങ്കിൽ എത്ര ദിവസം കൊണ്ട് ജോലി പൂർത്തിയാകും?