Challenger App

No.1 PSC Learning App

1M+ Downloads
5 men can complete a piece of work in 16 days while 2 women can do it in 20 days. In how many days can 4 women and 2 men complete it?

A4 days

B8 days

C13 days

D5 days

Answer:

B. 8 days

Read Explanation:

Understanding the Problem: Time and Work

This problem falls under the Time and Work section, a common topic in competitive exams. It requires calculating the combined effort of different individuals (men and women) with varying work efficiencies to complete a task.

Calculating Individual Efficiency

  • Men's Efficiency: 5 men complete a work in 16 days. This means the total work done by 5 men is equivalent to 1 unit of work in 16 days.

  • Therefore, the work done by 1 man in 1 day is $\frac{1}{5 \times 16} = \frac{1}{80}$ of the total work.

  • Women's Efficiency: 2 women complete the same work in 20 days.

  • Therefore, the work done by 1 woman in 1 day is $\frac{1}{2 \times 20} = \frac{1}{40}$ of the total work.

Calculating Combined Efficiency for the Target Group

We need to find the time taken by 4 women and 2 men to complete the work.

  • Work done by 2 men in 1 day: $2 \times \frac{1}{80} = \frac{1}{40}$ of the total work.

  • Work done by 4 women in 1 day: $4 \times \frac{1}{40} = \frac{1}{10}$ of the total work.

  • Total work done by 4 women and 2 men in 1 day: $\frac{1}{40} + \frac{1}{10} = \frac{1 + 4}{40} = \frac{5}{40} = \frac{1}{8}$ of the total work.

Calculating the Total Time

If $\frac{1}{8}$ of the work is completed in 1 day by 4 women and 2 men, then the total time required to complete the entire work is the reciprocal of this fraction.

  • Time taken = $\frac{1}{\frac{1}{8}}$ = 8 days.


Related Questions:

18 ആളുകള്‍ 36 ദിവസം കൊണ്ട് ചെയ്തു തീര്‍ക്കുന്ന ഒരു ജോലി 12 ആളുകള്‍ എത്ര ദിവസം കൊണ്ട് ചെയ്ത് തീര്‍ക്കും ?
Prakash and Vinesh can complete a certain piece of work in 10 and 8 days, respectively, They started to work together, and after 3 days, Vinesh left. In how many days will Prakash complete the remaining work?
Two inlet pipes A and B can fill a cistern in 30 minutes and 36 minutes, respectively. Initially, only A is opened for 10 minutes. After 10 minutes, A is closed and B is opened. In how much time (in minutes) will the inlet pipe B fill the remaining part of the cistern?
രാജൻ ഒരു ജോലി ചെയ്തു തീർക്കാൻ 10 ദിവസവും, ജോണി അതേ ജോലി ചെയ്തു തീർക്കാൻ 15 ദിവസവും എടുക്കും. എങ്കിൽ രണ്ടാളും ഒരുമിച്ച് ആ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും ?
2 പേർ, 20 ദിവസം കൊണ്ട് 10 അടി ഉയരമുള്ള ഒരു മതിൽ കെട്ടും. എങ്കിൽ അതേ മതിൽ കെട്ടാൻ 5 ആളുകൾ എത്ര ദിവസങ്ങളെടുക്കും ?