Challenger App

No.1 PSC Learning App

1M+ Downloads
5 men can complete a piece of work in 16 days while 2 women can do it in 20 days. In how many days can 4 women and 2 men complete it?

A4 days

B8 days

C13 days

D5 days

Answer:

B. 8 days

Read Explanation:

Understanding the Problem: Time and Work

This problem falls under the Time and Work section, a common topic in competitive exams. It requires calculating the combined effort of different individuals (men and women) with varying work efficiencies to complete a task.

Calculating Individual Efficiency

  • Men's Efficiency: 5 men complete a work in 16 days. This means the total work done by 5 men is equivalent to 1 unit of work in 16 days.

  • Therefore, the work done by 1 man in 1 day is $\frac{1}{5 \times 16} = \frac{1}{80}$ of the total work.

  • Women's Efficiency: 2 women complete the same work in 20 days.

  • Therefore, the work done by 1 woman in 1 day is $\frac{1}{2 \times 20} = \frac{1}{40}$ of the total work.

Calculating Combined Efficiency for the Target Group

We need to find the time taken by 4 women and 2 men to complete the work.

  • Work done by 2 men in 1 day: $2 \times \frac{1}{80} = \frac{1}{40}$ of the total work.

  • Work done by 4 women in 1 day: $4 \times \frac{1}{40} = \frac{1}{10}$ of the total work.

  • Total work done by 4 women and 2 men in 1 day: $\frac{1}{40} + \frac{1}{10} = \frac{1 + 4}{40} = \frac{5}{40} = \frac{1}{8}$ of the total work.

Calculating the Total Time

If $\frac{1}{8}$ of the work is completed in 1 day by 4 women and 2 men, then the total time required to complete the entire work is the reciprocal of this fraction.

  • Time taken = $\frac{1}{\frac{1}{8}}$ = 8 days.


Related Questions:

A and B together can do a certain work in x days. Working alone, A and B can do the same work in (x + 8) and (x + 18) days, respectively. A and B together will complete 5/6 of the same work in:
A and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work?
P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
There are two pipes leading to a tank. If pipe A alone is opened, the tank will be filled in 15 minutes. If pipe B alone is opened, the tank will be filled in 10 minutes. Both pipes were opened together. After 2 minutes, pipe B was closed. How long should pipe A be left open to fill the rest of the tank?
A, B, and C can do a piece of work in 42, 56, and 63 days respectively. They started the work together but A left the work 10 days before the completion of the work while B left the work 12 days before the completion. Find the number of days (approximate) to complete the whole work.