6 men can complete a work in 10 days. They start the work and after 2 days 2 men leave. In how many days will the work be completed by the remaining men?

A9

B7

C12

D8

Answer:

C. 12

Read Explanation:

Solution: Given: 6 men can complete a work in 10 days. 2 men leave after 2 days of work. Concept used: M1 × D1 = M2 × D2 Where M1 is no. of men working on D1 days and M2 is no. of men working on D2 days Calculation: Let, the work completed by remaining men be 'a'. According to the question, After 2 days, the remaining men = 6 - 2 = 4 Now, ⇒ 6 × 10 = 6 × 2 + 4 × a ⇒ 60 = 12 + 4a ⇒ 4a = 48 ⇒ a = 12 ∴ The remaining men will complete the work in 12 days.


Related Questions:

A can do a piece of work in 5 days, B in 10 days. How long will they take to do it together?
15 ജോലിക്കാർ 4 ദിവസം കൊണ്ട് ഒരു ജോലി ചെയ്തു തീർക്കുന്നു. അതേ ജോലി ചെയ്യാൻ 5 പേരുണ്ടെങ്കിൽ എത്ര ദിവസം വേണം ?
A, B and C can do a piece of work in 12 days, 14 days and 16 days respectively. All three of them started the work together and after working for four days C leaves the job, B left the job 4 days before completion of the work. Find the approximate time required to complete the work. (in days)
2 men and 5 women can do a work in 12 days. 5 men 2 women can do that work in 9 days. Only 3 women can finish the same work in-
400 തൊഴിലാളികൾക്ക് 75 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. അതിൽ നിന്ന് 25 തൊഴിലാളികളെ മാറ്റിയാൽ ആ ജോലി പൂർത്തിയാക്കാൻ എത്ര ദിവസം വേണ്ടിവരും ?