6 men can complete a work in 10 days. They start the work and after 2 days 2 men leave. In how many days will the work be completed by the remaining men?

A9

B7

C12

D8

Answer:

C. 12

Read Explanation:

Solution: Given: 6 men can complete a work in 10 days. 2 men leave after 2 days of work. Concept used: M1 × D1 = M2 × D2 Where M1 is no. of men working on D1 days and M2 is no. of men working on D2 days Calculation: Let, the work completed by remaining men be 'a'. According to the question, After 2 days, the remaining men = 6 - 2 = 4 Now, ⇒ 6 × 10 = 6 × 2 + 4 × a ⇒ 60 = 12 + 4a ⇒ 4a = 48 ⇒ a = 12 ∴ The remaining men will complete the work in 12 days.


Related Questions:

A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?
6 പുരുഷന്മാരും 8 സ്ത്രീകളും ചേർന്ന് 10 ദിവസം കൊണ്ട് ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും. ഒരു സ്ത്രീ ഒരു ദിവസം ചെയ്യുന്ന ജോലി ഒരു പുരുഷൻ ഒരു ദിവസം ചെയ്യുന്നതിൻ്റെ പകുതി ജോലിക്ക് തുല്യമാണ്. 10 സ്ത്രീകൾ ഒറ്റയ്ക്ക് ജോലി ചെയ്യുന്നുണ്ടെങ്കിൽ എത്ര ദിവസം കൊണ്ട് പണി പൂർത്തിയാകും?
Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?
ജോണും ദീപുവും ചേർന്ന് ഒരു ജോലി ചെയ്തു തീർക്കാൻ 45 ദിവസം എടുക്കുന്നു.എന്നാൽ ജോൺ ഒറ്റയ്ക്ക് ഈ ജോലി 70 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ദീപു ഒറ്റയ്ക്ക്ഇതേ ജോലി ചെയ്തു തീർക്കാൻ എത്ര ദിവസം എടുക്കും?
രണ്ട് പൈപ്പുകൾക്ക് യഥാക്രമം 12 മണിക്കൂറും 15 മണിക്കൂറും കൊണ്ട് ഒരു ടാങ്ക് നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും 4 മണിക്കൂർ തുറന്നു ആദ്യത്തെ പൈപ്പ് അടച്ചാൽ, ശേഷിക്കുന്ന ടാങ്ക് നിറയ്ക്കാൻ രണ്ടാമത്തെ പൈപ്പ് എടുക്കുന്ന സമയം കണ്ടെത്തുക