A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

A9 days

B16 days

C12 days

D11 days

Answer:

D. 11 days

Read Explanation:

Solution: Given: A can complete the work in 14 days B can complete the work in 21 days Concept: In this type of question always imagine the total work as LCM of time taken by individuals to perform the work. Formula used: Efficiency = Total work/Time taken Calculation: Let the total work be LCM of 21, 14 i.e 42 unit So, Efficiency of A = 42/14 = 3 unit/day Efficiency of B = 42/21 = 2 unit/day Efficiency of (A + B) = 5 unit/day According to Question, A and B work for 4 days and performed work = 4 × 5 = 20 unit Remaining work left = 42 – 20 = 22 unit B completes the remaining work = 22/2 = 11 days ∴ Time taken by B to complete the remaining work is 11 day


Related Questions:

A certain number of persons can finish a task in 85 days. If there were 15 persons more, it would have taken 25 days less for the task to be completed. How many persons are there in the beginning?
Anjani can do a certain piece of work in 18 days. Anjani and Khushbu can together do the same work in 14 days, and Anjani, Khushbu and Sushmita can do the same work together in 9 days. In how many days can Anjani and Sushmita do the same work?
A ഒരു ജോലി 60 ദിവസത്തിലും B 20 ദിവസത്തിലും ചെയ്യുന്നു. രണ്ടുപേരും ചേർന്ന് എത്ര ദിവസത്തിനുള്ളിൽ ജോലി പൂർത്തിയാക്കും?
ഒരു തീവണ്ടി ഒരു ടെലഗ്രാഫ് പോസ്റ്റ് 8 സെക്കൻഡ് കൊണ്ടും 105 മീറ്റർ നീളമുള്ള പാലം 20 സെകണ്ട് കൊണ്ടും കടന്നുപോകുന്നു. തീവണ്ടിയുടെ നീളം എത്ര ?
A can do a work in 12 days, B can do it in 20 days and C in 15 days. If they work together the number of days needed to complete the work is: