App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

A9 days

B16 days

C12 days

D11 days

Answer:

D. 11 days

Read Explanation:

Solution: Given: A can complete the work in 14 days B can complete the work in 21 days Concept: In this type of question always imagine the total work as LCM of time taken by individuals to perform the work. Formula used: Efficiency = Total work/Time taken Calculation: Let the total work be LCM of 21, 14 i.e 42 unit So, Efficiency of A = 42/14 = 3 unit/day Efficiency of B = 42/21 = 2 unit/day Efficiency of (A + B) = 5 unit/day According to Question, A and B work for 4 days and performed work = 4 × 5 = 20 unit Remaining work left = 42 – 20 = 22 unit B completes the remaining work = 22/2 = 11 days ∴ Time taken by B to complete the remaining work is 11 day


Related Questions:

Jitesh and Kamal can complete a certain piece of work in 7 and 16 days, respectively, They started to work together, and after 2 days, Kamal left. In how many days will Jitesh complete the remaining work?
A and B can complete a piece of work in 10 days and 12 days, respectively. If they work on alternate days beginning with A, then in how many days will the work be completed?
Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes are opened simultaneously, after how much time should A be closed so that the tank is full in 20 minutes?
Vijayan can do a job in 25 days and Achyuth can do it in 20 days. Vijayan started the work and Achyuth joined af. ter 15 days and Vijayan left. How many days did Achyuth take to complete the ramaining job?
A can finish 3/5th of a task in 6 days and B can finish 2/3th of the same task in 12 days. A and B worked together for 5 days. C alone completed the remaining task in 8 days. B and C, working together, will complete the same task in: