A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work?

A9 days

B16 days

C12 days

D11 days

Answer:

D. 11 days

Read Explanation:

Solution: Given: A can complete the work in 14 days B can complete the work in 21 days Concept: In this type of question always imagine the total work as LCM of time taken by individuals to perform the work. Formula used: Efficiency = Total work/Time taken Calculation: Let the total work be LCM of 21, 14 i.e 42 unit So, Efficiency of A = 42/14 = 3 unit/day Efficiency of B = 42/21 = 2 unit/day Efficiency of (A + B) = 5 unit/day According to Question, A and B work for 4 days and performed work = 4 × 5 = 20 unit Remaining work left = 42 – 20 = 22 unit B completes the remaining work = 22/2 = 11 days ∴ Time taken by B to complete the remaining work is 11 day


Related Questions:

Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?
10 പുരുഷന്മാർ ഒരു ജോലി 12 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കാൻ കഴിയുമെങ്കിൽ അതെ ജോലി ചെയ്യാൻ 12 പുരുഷന്മാർ എടുക്കുന്ന സമയം എത്ര?
54kg ധാന്യം 35 കുതിരകൾക്ക് 21 ദിവസത്തേക്ക് തികയുമെങ്കിൽ 72kg ധാന്യം 28 കുതിരകൾക്ക് എത്ര ദിവസത്തേക്ക് തികയും?
A can do a work in 12 days. When he had worked for 3 days, B joined him. If they complete the work in 3 more days, in how many days can B alone finish the work?
Working alone, A can do a job in 15 days and B can do the same job in 18 days. In how many days will the job be completed if both work together?