App Logo

No.1 PSC Learning App

1M+ Downloads
Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?

A32 days

B40 days

C45 days

D60 days

Answer:

B. 40 days

Read Explanation:

P alone can do it in 10 days , $Efficiency of P =\frac{1}{10}$

Q alone can do it in 24 days,

EfficiencyofQ=124Efficiency of Q =\frac{1}{24}

Together they can do it in 6days

$Efficiency of Q=\frac{1}{6}$

$\frac1{10}+\frac{1}{24}+\frac{1}{R}=\frac{1}{6}$

$\frac1{R}=\frac{1}{40}$

$R=40 Days$

Alternate method

image.png

EffrciciencyofP+Q+R=20Effrciciency of P+Q+R=20

R=20(12+5)R=20-(12+5)

EfficiencyofR=3Efficiency of R=3

$$Time taken by R alone to complete a work is$=\frac{120}{3} = 40 days$


Related Questions:

A fort is provisioned for 32 days for some soldiers. After 4 days, a reinforcement of 150 soldiers arrived and the food will now last for 21 days only. How many soldiers were there in the fort in the beginning?
ഒരു നിശ്ചിത എണ്ണം ജോലിക്കാർ 100 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 10 ജോലിക്കാരുടെ കുറവുണ്ടായാൽ 10 ദിവസം കൂടി ചെയ്താൽ മാത്രമേ പൂർത്തിയാവുകയുള്ളൂ. എങ്കിൽ ജോലിക്കാരുടെ എണ്ണമെത്ര ?
One pipe can fill a tank three times as fast as another pipe. If together the two pipes can fill the tank in 36 minutes, then the slower pipe alone will be able to fill the tank in :
P works twice as fast as Q. Q alone can complete some work in 12 days. Working together, how long will P and Q take to complete the work?
The efficiency of A and B to do a work is in the ratio 3 ∶ 5. Working together they can complete a work in 30 days. In how many days A alone will complete that work?