App Logo

No.1 PSC Learning App

1M+ Downloads
Working together, P, Q and R reap a field in 6 days. If P can do it alone in 10 days and Q in 24 days, in how many days will R alone be able to reap the field?

A32 days

B40 days

C45 days

D60 days

Answer:

B. 40 days

Read Explanation:

P alone can do it in 10 days , $Efficiency of P =\frac{1}{10}$

Q alone can do it in 24 days,

EfficiencyofQ=124Efficiency of Q =\frac{1}{24}

Together they can do it in 6days

$Efficiency of Q=\frac{1}{6}$

$\frac1{10}+\frac{1}{24}+\frac{1}{R}=\frac{1}{6}$

$\frac1{R}=\frac{1}{40}$

$R=40 Days$

Alternate method

image.png

EffrciciencyofP+Q+R=20Effrciciency of P+Q+R=20

R=20(12+5)R=20-(12+5)

EfficiencyofR=3Efficiency of R=3

$$Time taken by R alone to complete a work is$=\frac{120}{3} = 40 days$


Related Questions:

If 3 men or 4 women can plough a field in 43 days, how long will 7 men and 5 women take to plough it ?
ഒരു നിശ്ചിത എണ്ണം ജോലിക്കാർ 100 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 10 ജോലിക്കാരുടെ കുറവുണ്ടായാൽ 10 ദിവസം കൂടി ചെയ്താൽ മാത്രമേ പൂർത്തിയാവുകയുള്ളൂ. എങ്കിൽ ജോലിക്കാരുടെ എണ്ണമെത്ര ?
A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days A finished the remaining work. In how many days A alone can finish the job?
20 buckets of water fill a tank when the capacity of each bucket is 13.5 litres. How many buckets will be required to fill the same tank ifthe capacity of each bucket is 9 litres?
5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?