App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

Ganesh, Ram and Sohan together can complete a work in 16 days. If Ganesh and Ram together can complete the same work in 24 days, the number of days Sohan alone takes, to finish the work is
A യും B യും ചേർന്ന് 20 ദിവസം കൊണ്ട് ഒരു പ്രവൃത്തി ചെയ്യാൻ കഴിയും. അവർ ഒരുമിച്ച് പ്രവൃത്തി ആരംഭിക്കുന്നു, പക്ഷേ പ്രവൃത്തി പൂർത്തിയാകുന്നതിന് 5 ദിവസം മുമ്പ് A യ്ക്ക് വിട്ടുപോകേണ്ടി വരുന്നു. ബാക്കിയുള്ള പ്രവൃത്തി 18 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ B യ്ക്ക് കഴിയുമെങ്കിൽ, B ഒറ്റയ്ക്ക് എത്ര ദിവസം കൊണ്ട് മുഴുവൻ പ്രവൃത്തിയും പൂർത്തിയാക്കും?
ഒരു നിശ്ചിത ദൂരം പിന്നിടാൻ എടുക്കുന്ന സമയം 20 % കുറക്കാൻ ഒരു ഓട്ടക്കാരൻ തന്റെ വേഗത എത്ര ശതമാനം വർധിപ്പിക്കണം ?
ബാബു ഒരു ജോലി 12 ദിവസം കൊണ്ടും, രമ ആ ജോലി 6 ദിവസം കൊണ്ടും ചെയ്യും. അവർ ഇരുവരും ചേർന്ന് ജോലി ചെയ്യാനെടുക്കുന്ന ദിവസമെത്ര ?
32 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കുവാൻ 15 ദിവസം വേണമെങ്കിൽ 10 ദിവസം കൊണ്ട് ആ ജോലി പൂർത്തീകരിക്കുവാൻ എത്ര ആളുകൾ വേണം ?