App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

5 പുരുഷൻമാർ 3 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്ന ഒരു ജോലി, 4 സ്ത്രീകൾ 6 ദിവസം കൊണ്ടാണ് ചെയ്തു തീർക്കുന്നത്. ആ ജോലി അവർ ഒന്നിച്ചു ചെയ്താൽ എത്ര ദിവസം കൊണ്ടാണ് പൂർത്തിയാകുന്നത് ?
Sita is twice efficient than Gita. If together they complete the work in 15 days. Find the difference of number of days between Gita and Sita.
സന്ധ്യ ഒരു ജോലി 20 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കും. ഗോപു അതു ചെയ്യാൻ 60 ദിവസം എടുക്കും. എങ്കിൽ രണ്ടു പേരും ചേർന്നാൽ ആ ജോലി എത്ര ദിവസം കൊണ്ട് പൂർത്തിയാക്കും ?
A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete 4/9 part of the original work in:
A filling pipe can fill a pot in 40 minutes and wastage pipe can empty the filled pot in 60 minutes. By mistake without closing the wastage pipe, the filling pipe opened. In how much time an empty pot can be filled?