Challenger App

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

P and Q together can complete a work in 20 days. If P alone can complete the same work in 36 days, then in how many days Q alone can complete the same work?
Suresh can complete a job in 15 hours. Ashutosh alone can complete the same job in 10 hours. If Suresh works alone for 9 hours and then stops, how many hours will it take Ashutosh to complete the job alone?
A fort had provision of food for 150 men for 85 days. After 15 days, 25 men left the fort. Find the number of days for which the remaining food will last.
Raj alone can do a piece of work in 8 days. Raman alone can do it in 12 days. If the total wage for the work is Rs. 500. How much should Raj be paid if they work together for the entire duration of the work?
Two pipes A and B can fill a tank in 12 and 16 minutes respectively. Both the pipes are opened together but 4 minutes before the tank is full pipe A is closed in how many minutes the tank will totally fill?