App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

12 പുരുഷന്മാരോ,18 സ്ത്രീകളോ ഒരു ജോലി 14 ദിവസം കൊണ്ട് ചെയ്തു തീർക്കുന്നു. എന്നാൽ 8 പുരുഷന്മാരും 16 സ്ത്രീകളും ചേർന്ന് അതേ ജോലി എത്ര സമയത്തിനുള്ളിൽ ചെയ്തു തീർക്കും ?
If I had time, I
7 ആളുകൾക്ക് ഒരു ജോലി പൂർത്തിയാക്കാൻ '6' ദിവസം വേണം. അതേ ജോലി ഒരു ദിവസം കൊണ്ട്പൂർത്തിയാക്കാൻ എത്ര ആൾക്കാർ വേണം?-
4 പുരുഷന്മാർക്കും 5 സ്ത്രീകൾക്കും 15 ദിവസത്തിനുള്ളിൽ ഒരു ജോലി പൂർത്തിയാക്കാൻ കഴിയും, അതേസമയം 9 പുരുഷന്മാർക്കും 6 സ്ത്രീകൾക്കും 10 ദിവസം കൊണ്ട് അത് പൂർത്തിയാക്കാൻ കഴിയും. ഇതേ ജോലി 7 ദിവസം കൊണ്ട് പൂർത്തിയാക്കാൻ, 4 പുരുഷന്മാരെ എത്ര സ്ത്രീകൾ സഹായിക്കണം?
ഒരു നിശ്ചിത എണ്ണം ജോലിക്കാർ 100 ദിവസം കൊണ്ട് ചെയ്ത് തീർക്കുന്ന ജോലി 10 ജോലിക്കാരുടെ കുറവുണ്ടായാൽ 10 ദിവസം കൂടി ചെയ്താൽ മാത്രമേ പൂർത്തിയാവുകയുള്ളൂ. എങ്കിൽ ജോലിക്കാരുടെ എണ്ണമെത്ര ?