App Logo

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

A and B can complete a piece of work in 8 days, B and C can do it in 12 days, C and A can do it in 8 days. A, B and C together can complete it in
A and B together take 5 days to do work, B and C take 7 days to do the same, and A and C take 4 days to do it. Who among these will take the least time to do it alone?
A tap can fill a tank in 8 hours. After half the tank is filled, four more similar taps are opened. What is the total time taken to fill the tank completely?
ഒരു പൈപ്പിന് മറ്റൊരു പൈപ്പിനേക്കാൾ മൂന്നിരട്ടി വേഗത്തിൽ ടാങ്കിൽ നിറയ്ക്കാനാകും. രണ്ട് പൈപ്പുകളും ചേർന്ന് 36 മിനിറ്റിനുള്ളിൽ ടാങ്ക് നിറയ്ക്കാൻ കഴിയുമെങ്കിൽ, വേഗത കുറഞ്ഞ പൈപ്പിന് എത്ര നേരം കൊണ്ട് ടാങ്ക് നിറക്കാം?
Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day?