Challenger App

No.1 PSC Learning App

1M+ Downloads
A alone can complete the project in 10 days; B alone can complete it in 20 days while C alone can complete it in 30 days. They together earn Rs. 1,100 for the project. By how much do the total earnings of A and C exceed the earnings of B?

ARs. 600

BRs. 900

CRs. 700

DRs. 500

Answer:

D. Rs. 500

Read Explanation:

Solution: Given: A's time = 10 days, B's time = 20 days, C's time = 30 days, Total earning = Rs. 1,100 Concept Used: Work done is inversely proportional to time Calculation: ⇒ A's work/day : B's work/day : C's work/day = 1/10 : 1/20 : 1/30 = 6 : 3 : 2 ⇒ Earnings of A and C = (6 + 2)/11 × Rs. 1,100 = Rs. 800 ⇒ Earnings of B = 3/11 × Rs. 1,100 = Rs. 300 ⇒ Difference = Rs. 800 - Rs. 300 = Rs. 500 Therefore, the total earnings of A and C exceed the earnings of B by Rs. 500. ∴ Option 4 is the correct answer.


Related Questions:

Two pipes A and B can fill a tank in 24 minutes and 32 minutes respectively. If both the pipes are opened simultaneously, after how much time should A be closed so that the tank is full in 20 minutes?
P is twice as efficient as Q. Q takes 12 days to complete a job. If both of them work together, how much time will they take to complete the job?
ഒരു കമ്പ്യൂട്ടർ ലാബിൽ 6 കൂട്ടികൾക്ക് 3 കമ്പ്യൂട്ടർ ഉണ്ട്. 24 കൂട്ടികൾക്ക് എത്ര കമ്പ്യൂട്ടർ ഉണ്ടാവും?
Two pipes A and C can fill a tank in 10 hours and 15 hours respectively. If A is open all the time and C is open for 30 minutes, then find the time needed for the tank to be filled.
X, Y and Z can complete a piece of work in 46 days, 92 days and 23 days, respectively. X started the work. Y joined him after 7 days. If Z joined them after 8 days from the beginning, then for how many days did Y work?